January 13, 2011 ROAD WORK WEEKLY REPORT Scheduled road work for the week beginning January 16, 2011, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below. Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted. AIEA Local Rehabilitation of Streets, Phase 1 (IDIQ#2). Paving Keeamoku St. from Kaihee St to Mauka End and Kalihi St from Maliu St to Mauka End. AINA HAINA Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Aina Haina: The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Hind Iuka Dr from Mona St to End slurry seal is done. (Estimated completion date, June 2013) EWA Miscellaneous Drainage Improvements at Various Locations (Pohakupuna Road). Construct additional drain manholes on the existing drain line. (Estimated completion date, January 2011 HALAWA Rehabilitation of Secondary Streets at Pearl City Ulune Street (Kahuapaani Street to Kulawea Street), Aiealani Place (Halawa Heights Road to end), Fernridge Place (Halawa Heights Road to end), Halawa Heights Road (Fernridge Place to Mauka end), Hele Mauna Place (Halawa Heights Road to end), Kaimakani Street (Moanalua Road to Ulune Street), Palaialii Place (Halawa Heights Road to end), and Palaialii Way (Palaialii Place to end): Paving completed. Punch list for manhole adjustment remaining. (Estimated completion date, January 2011) HAWAII KAI Curb Ramps at Various Locations, FY 2008 (X), Kaumakani Street / Lunalilo Home Road, Kalanipuu Street / Lunalilo Home Road: Construction of new curb ramps, sidewalks and A.C. transition. Relocation of existing regulatory / street signs. Installation of new Heco handhole and conduits. Adjustment of Heco pullbox. Installation of pavement striping, markings and markers. (Estimated completion date, January 2011) HONOLULU Rehabilitation of Secondary Streets at Ala Wai: The project includes excavating, reconstructing and resurfacing asphalt concrete pavements and base; providing smooth lateral transitions at all streets and driveways; reconstructing base at bus stop locations; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings. The affected roadways and limits of work are as follows: Kapiolani Boulevard: From Date Street to South King Street is being paved. Isenberg Street: From Kapiolani Boulevard to Bingham Street, paving completed. (Estimated completion date, January 2011) Amelia Street Relief Sewer Amelia Street and adjoining School Street: Installation of a new 16" sewer line underground along Amelia Street and portion of School Street at Amelia Street (Estimated completion date, January 2011) Iolani Avenue Retaining Wall: Construction of new CRM fence wall and installation of soil nail tie backs and reinforced shotecrete facing on retaining wall at 625 Iolani Avenue fronting Dole Community Garden. Restore A.C. sidewalk fronting new CRM wall. Remove existing trees and re-plant new trees in Dole Community Garden. (Estimated completion date, January 2011) Iwilei Road and North King Street Drainage Improvements Intersection of Iwilei Road and North King Street: Repair 18-inch and 12-inch drain lines, pavement restoration work, curb, gutter and sidewalk restoration, striping, and pavement marking restoration, the construction of sewer jackets and the reconstruction of a curb ramp flare. (Estimated completion date, June 2011) Rehabilitation of Localized Streets, Phase 5A Kahala to Kaimuki Area Post Paving Activities in-progress. The work includes permanent pavement markings and adjustment of utility manhole frames and covers to grade. The affected roadways and limits of work are as follows: 18th Avenue, from Harding Avenue to Diamond Head Road, 19th Avenue, from H-1 Freeway to Kilauea Avenue including TMK: 32039051, 20th Avenue, from H-1 Freeway to Kilauea Avenue, 21st Avenue, from Harding Avenue to Kilauea Avenue, 22nd Avenue, from Harding Avenue to End, Ahakea, Street, from Aukai Avenue to Elepaio Street, Ahina Street, from Ahakea Street to Aukai Avenue, Ahuli Place, from Pahoa Avenue to End, Alae Street, from Elepaio Street to Onaha Street, Amau Street, from Hunakai Street to Pueo Street, Apuwai Place, from Kilauea Avenue to End, Aukai Avenue, from Kealaolu Avenue to Kahala Avenue Elepaio Street, from Kilauea Avenue to Kahala Avenue, Farmers Road, from Kealaolu Avenue to Ulumaika Street, Hakaka Place, from Hakaka Street to End, Hakaka Street, from Palekaua Street to End, Honua Street, from Onaha Street to Kolohala Street, Hopeloa Place, from Puu Panini Avenue to End, Huanui Place, from Huanui Street to End, Huanui Street, from 22nd Avenue to Puu Panini Avenue including TMK: 32061018, Hunakai Street, from Waialae Avenue to Kahala Avenue, Hunalewa Street, from 22nd Avenue to Huanui Street, Hunapaa Street, from Huanui Street to End, Iiwi Street, from, Onaha Street to Kolohala Street, Ipo Place, from 22nd Avenue to End Kaalawai Place, from Diamond Head Road to End, Kaikoo Place, from Papu Circle to End, Kaikuono Place, from Papu Circle to End, Kaimanahila Street, from Paikau Street to Hakaka Street, Kaimuki Avenue, from 18th Avenue to Luawai Street, Kala Place, from Aukai Avenue to Kahala Avenue, Kaualio Place, from 22nd Avenue to End, Kealaolu Place, from Kealaolu Avenue to End, Koae Place, from Koae Street to End, Koae Street, from Hunakai Street to Amau Street, Koloa Street, from Kahala Avenue to Elepaio Street, Kolohala Street, from Onaha Street to Elepaio Street, Kuana Street, from Onaha Street to Kolohala Street, Kulamanu Street, from Kahala Avenue to Kulamanu Place Luakaha Place, from Luakaha Street to End, Luakaha Street, from Luawai Street to End, Luawai Place, from Luawai Street to End, Luawai Street, from 20th Avenue to Pahoa Avenue, Makaiwa Street, from Kilauea Avenue to Pueo Street, Makalike Place, from 22nd Avenue to End, Malapua Place, from 22nd Avenue to End, Maunaloa Avenue, from 18th Avenue to 22nd Avenue, Moa Street, from Pueo Street to Makaiwa Street, Noio Street, from Onaha Street to Kolohala Street, Onaha Street, from Kilauea Avenue to Kolohala Street Pahoa Avenue, from Kilauea Avenue to Moa Street and from 18th Avenue to 22nd Avenue, Paikau Street, from 22nd Avenue to Kahala Avenue, Palekaua Place, from Palekaua Street to End, Palekaua Street, from Puu Panini Avenue to Hakaka Street, Pana Place, from Paikau Street to End, Panini Loop, from Puu Panini Avenue to Puu Panini Avenue, Pilialo Street, from Luawai Street to Kaimuki Avenue Poka Place, from Poka Street to End, Poka Street, from Paikau Street to Diamond Head Road, Pokapahu Place, from Paikau Street to End, Pueo Street, from Kahala Avenue to Hunakai Street, Puulani Place, from Hunakai Street to End, Puu Panini Avenue, from Kilauea Avenue to 22nd Avenue, Ulili Street, from Onaha Street to Kahala Avenue, Ulumaika Street, from Hunakai Street to Hunakai Street, Ulupua Place, from 22nd Avenue to End, Waikui Street, off Kalanianaole Highway, Waiohinu Drive, from Makaiwa Street to Makaiwa Street (Estimated Completion January 2011) Kalihi/Nuuanu Area Sewer Rehabilitation Phase 1A and 1C: New sewer line and manhole installation on Dillingham Blvd, Puuhale Road, Mokauea Street, and Kalihi Street. Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m. (Estimated completion date, January 2011) Kalihi/Nuuanu Area Sewer Rehabilitation Phase 1B: New sewer line and manhole installation on Akina and Kaili Street. Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m. (Estimated completion date, January 2011) Kalihi/Nuuanu Area Sewer Rehabilitation Phase 1D: New sewer line and manhole installation on Booth Road and Prospect Street. Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m. (Estimated completion date, January 2011) Kalihi/Nuuanu Area Sewer Rehabilitation Phase 1G: New sewer line, manhole installation and sidewalk restoration on Kuakini Street (between Nuuanu Avenue and Pali Highway) is ongoing. Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m. (Estimated completion date, January 2011) Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Kapahulu: 4th ave, 5th ave, Hookipa Way, Pahoa Ave, Kaimuki Ave, Olu St, Mokihana St, Paliuli St and Charles St. and Kulamanu Pl. The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Olu St from 4th ave to 6th ave, Mokihana St from 4th ave to Mooheau ave and Kulamanu Pl from Kulamanu St to End are done. (Estimated completion date, June 2013) Rehabilitation of Secondary Streets at Makiki - Kinau St from Alapai St to Waiau Pl, Wilder Ave from Spencer St to Dole St. and Dole St from Wilder Ave to St. Louis Dr.: The project will demolish, remove and dispose of existing pavements in Honolulu area. Resurface or reconstruct these streets with asphalt concrete pavement. Adjust manholes and monuments to road grades. Restore all pavement striping, markings and markers. Collect GPS data on manholes, street monuments, valve boxes, fire hydrants, and other features as directed by the City before construction begins. Work is currently being done on Wilder Avenue near the Punahou Intersection. (Estimated completion date, March 2011) Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program. Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves. Re-grade swale and adjust DI to provide positive drainage into existing drain system. Upgrade concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams. At the intersection of Ahua Street and Awaawaloa Street, abandon existing storm drain on Ahua Street and install new storm drain MH on upstream end of abandoned pipe. (Estimated completion date, January 2011) Mokauea Street Improvements between North King Street and Dillingham Boulevard: Reconstruction concrete curbs and gutters, driveway and some sidewalks; construct new curb ramps; reconstruct and resurface asphalt roadway. Post paving activities include installation of permanent pavement markings, adjust utilities to finish grade, and re-install traffic loop detectors. (Estimated Completion April 2011) Curb Ramps at Various Locations, FY 2009 (B), Palolo and Kaimuki: Construction of new curb ramps, sidewalks and A.C. transition. Relocation of existing regulatory/street signs. Installation of pavement striping, markings and markers. (Estimated completion date, June, 2011) Rehabilitation of Secondary Streets at Kaimuki Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street. Paving completed, working on manhole adjustments. (Estimated completion date, January 2011) Peterson Lane and Pua Lane Sewer Rehabilitation: New sewer line and manhole installation in complete on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane. Repaving of King, Peterson and Pua Lane is complete. Punchlist items and reconstruction of Tamashiro Market driveway remain. One lane in each direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m. (Estimated completion date, January 2011) Punchbowl Street and Lusitana Street Drainage Improvements: The work consists of drainlines and manholes rehabilitation with Cast-in-place-pipe (CIPP) in Punchbowl Street, and 24-inch drainline and curb replacement in Lusitana Street. One lane road closure will be limited to 8:30 a.m. to 3:30 p.m., Monday thru Friday, except for County furlough and holidays. Work will begin in December 2010. (Estimated completion date, February 2011) Saint Louis Heights Sewer Rehabilitation: Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights. The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street. (Estimated completion date, January 2011) Sewer rehabilitation on various streets on Wilhelmina Rise. Installation of cured in place pipe (CIPP), lateral rehailitation, and replacement of sewer lines by open trench. (Estimated completion date January 2011) KAILUA Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Aikahi Park. The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Slurry seal is in process. (Estimated completion date, June 2013) Kalaheo Avenue/Mokapu Road/Aikahi Loop Sewer Rehabilitation: Installation of Cured In Place Pipe along Mokapu Boulevard, from the intersection of Mokapu and Kalaheo, and Aikahi Loop. (Estimated completion date, January 2011) Rehabilitation of Kawailoa Road Bridge over Kaelepulu Stream, Bridge No. 411: Work includes repair of spalls in the concrete elements; replacement of the deteriorated pedestrian walkway and railing at the upstream side of the bridge; repair of deck joints; replacement of the vehicular guardrail system; and traffic safety improvements at the bridge approaches. (Estimated completion date, January 2011) Rehabilitation of Streets, Unit 52 Keolu Drive (Kalanianaole Highway to Akahai Street); Keolu Drive (Akaakaawa Street to Wanaao Road): Cold planing; resurfacing and reconstruction of asphalt concrete pavements (ACP); adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, sidewalks and Driveways; reconstruction of concrete catch basins; and construction of concrete and asphaltic concrete bus pads. (Estimated completion date, January 2011) Wanaao Road/Keolu Drive Reconstructed Sewer: Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road. (Estimated completion date, January 2011) KANEOHE Curb Ramps at Various Locations, FY 2009 (X) Hui Iwa Street / Hui Kelu Street / Hui Aeko Street: Construction of new curb ramps, sidewalks and A.C. transition. Relocation of existing stop sign. Installation of pavement striping, markings and markers. (Estimated completion date, January 2011) Rehabilitation of Kamehameha Highway Bridge Over Heeia Stream Kamehameha Highway in Heeia: Repair of concrete delamination, spalls and cracks on existing bridge structure; removal and replacement of sidewalk platform; painting of the bridge parapet, chain link fence, and sidewalk's steel structure. (Estimated completion date, June 2011) Flood Control Improvements at Various Locations FY 2008 Kaneohe, Kailua & Waipio: Demolish and reconstruct new concrete and asphalt concrete ramps and driveways. Repair existing concrete ditch and adjust utility frames, covers and boxes to finish grade. (Estimated completion date, May, 2011) Kaneohe Bay Drive Trunk Sewer Reconstruction: Installation of new sewer lines, new manholes, and cured in place pipe (CIPP). Work will occur on Kaneohe Bay Drive between Mokapu Road and Kuono Place, Kaimalu Place and Way, Ikeanani Drive, and Kuakoa Place. (Estimated completion date January 2011) Kapunahala Road Retaining Wall near 45-866 Anoi Road Construction of a concrete retaining wall and railing. Restore AC pavement, AC sidewalk and AC curb. Traffic detours will be provided after working hours. (Estimated completion date, January 2011) Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Kaneohe: Mokulele Dr and Kaneohe Bay Dr. The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Slurry seal is in process. (Estimated completion date, June 2013) MAKAKILO Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Honokai Hale. The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Crack sealing is in process. (Estimated completion date, June 2013) MANOA Manoa Valley Drainage Improvements at 3088 and 3090 Kahewai Place: Removal of existing concrete headwall and drain pipe, installation of new drain manhole and 18" RCP drain pipe, and construction of CRM drain outlet structure and base. (Estimated completion date, January 2011) Miscellaneous Drainage Improvements at Various Locations (Loulu Street). Construct concrete drain inlets, connect to existing catch basin, and install drain pipes and cleanouts. (Estimated completion date, January 2011) NUUANU Rehabilitation of Kimo Drive Bridge Over Nuuanu Stream, Bridge No. 260 Repair of spalls, concrete guardrails and bridge girders. (Estimated completion date, January 2011) PALOLO Rehabilitation of Secondary Streets at Kaimuki Palolo Avenue, Waialae Avenue to 10th Avenue in Palolo Valley. Paving completed, working on manhole adjustments. (Estimated completion date, January 2011) PEARL CITY Rehabilitation of Secondary Streets at Pearl City Hoolaulea Street below Moanalua Road (Waimano Home Road to Hoomoe Road), Nanakai Place (Nanakai Street to end), Nanakai Street (Waimano Home Road to Hoomalu Street), Puu Kipa Street ( Nanakai Street to Nanakai Street): Paving completed. Punch list for manhole adjustment remaining. (Estimated completion date, January 2011) Manana Infrastructure Improvements, Phase VI Connector Road (Kuala Street to Kuahaka Street) Construct 60-foot wide roadway from Kuala Street to Kuahaka Street. The work includes, vector control; clearing, grubbing and grading; installation of new storm drain, Heco, Hawaiian Telcom, street light and traffic signal systems; concrete slab protection for existing sewer and water lines; grade adjustments in private lots; new noise and retaining walls, chain link fence and gates: reconstruction of existing drain, water and sewer MHs and valves to new finish grade; installation of curbs, gutters, sidewalks, driveways, curb ramps and sidewalk culverts; installation of irrigation system and landscape improvements; tree removal and pruning in private lots; road paving; pavement markings and markers and street signs. (Estimated completion date, January 2011) Waimalu Sewer Rehabilitation/Reconstruction Phase I: Installation of new sewer lines/man holes and reconnection of existing sewer laterals along Hekaha, Kanuku, Lokowai, Lii-Ipo, Pahemo, and Olepe. (Estimated completion date, January 2011) Protective Chain Link Fencing at Various Locations, FY-04 Waimano Home Road: Removal and replacement of CMU wall, guardrails and chain link fence. (Estimated completion date, March 2011) PEARLRIDGE Rehabilitation of Secondary Streets at Pearl City Kaonohi Street ( Kaonohi Place to entire loop), and Kaonohi Street (Kamehameha Highway to Moanalua Road): Paving completed. Punch list for manhole adjustment remaining. (Estimated completion date, January 2011) PUPUKEA Pupukea Road Rockfall Mitigation Phase I Pupukea, Oahu: The work consists of clearing vegetation within the project limits, scaling boulders and unstable rocks or installing rock dowels (where appropriate), applying shotcrete (where required), installing rock fall protection fences, drapery system and landscaping. One traffic lane will be closed during work hours at Pupukea Road with police performing traffic control duties. Actual construction work will start on Monday March 14, 2011. (Estimated completion date, August 2011) SALT LAKE Protective Chain Link Fencing at Various Locations, FY-04 Luaole Street: Removal of damaged fence and installation of new chain link fence and posts. (Estimated completion date, March 2011) WAHIAWA Rehabilitation of Streets, Unit 58 California Avenue (Kamehameha Highway to mauka end of California Avenue): Cold planing; resurfacing and reconstruction of asphalt concrete pavement; adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, berms, sidewalks and Driveways; and construction of concrete and asphalt concrete bus pads. (Estimated completion date, December 2011) WAIANAE Mailiili Stream Flood Control Improvements Near Halona Road and Puuhulu Road: Removal and reconstruction of damaged concrete channel lining, construction of new channel access ramp near Halona Road Bridge, and construction of overflow side-drains on the channel banks. (Estimated completion date, July 2011) Mailiili Stream Restoration Near Mailiili Road: Removal of fill material including concrete rubble, uncompacted material, asphalt concrete, etc., removal of access ramp, installation of erosion control blanket on stream banks, and planting of channel bed with wetland vegetation. Implementation, maintenance and removal of BMPs. (Estimated completion date, February 2011) WAIKIKI Rehabilitation of Secondary Streets at Kaimuki Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street. Paving completed, working on manhole adjustments. (Estimated completion date, January 2011) WAIPAHU Rehabilitation of Paiwa Street (Farrington Highway to Waipahu Street), Waipahu Street (Hianakiu Street to Kaupu Place), Makoa Street (Puia Street to end to end), Puia Street (Anonui Street to Eleu Street, and Heahea Street to deadend): Paving completed. Punch list for manhole adjustment remaining. (Estimated completion date, January 2011) PARADES, WALKS, RACES AND OTHER STREET CLOSURES January 10-16, 2011 7 days a week 6:30AM Starts 5:30PM Ends | SONY OPEN GOLF TOURNAMENT IN HAWAII by Sony Open In Hawaii. Avoid Kahala area because of increased traffic. NO PARKING AREAS: 1) KAHALA AVENUE, odd address side, Pueo Ave to Kealaolu Ave (for shuttle bus), 2) KAHALA AVENUE, both sides, Kealaolu Ave to golf course property, 3) PUEO STREET,odd address side, Kahala Ave to Aukai Ave (for shuttle bus), 4) 18th AVENUE even address side, near Iwalani Pl., fronting Hawaii Film Studio (for shuttle bus), 5)FARMERS ROAD, odd address side, 4777 (one-half block from Kealaolu Ave) to Kealaolu Ave. 6) FARMERS ROAD, even address side, Kealaolu Ave to Makaiwa St.,7) KAIMOKU PLACE,golf course side, from Kaimoku Way to makai property line of 1108 Kaimoku Pl., 8) KAIMOKU PLACE, odd address side, for its entire length, including the cul-de-sac, 9) KAIMOKU WAY, both sides for its entire length, 10) KEALAOLU AVENUE, both sides, Waialae Ave to Kahala Ave., 11) KEALAOLU PLACE, odd address side, for its entire length, 12)MAKAIWA STREET, odd address side, Kilauea Ave to Farmers Rd.,13) MAKAIWA STREET, even address side, Farmers Road to Pueo St.,14) MOHO STREET, odd address side, for its entire length. Contact: Sony Open in Hawaii 808-523-7888 Email: friend@friendsofhawaii.org For more info, visit their website: http://www.sonyopeninhawaii.com/index.html | January 15-16, 2011 Saturday-Sunday 6:00AM Starts 6:00PM Ends | HURT TRAIL 100 sponsored by HURT. The event is expected to have 80 participants. It will start at Hawaii Nature Center via trail to Paradise Park in Manoa, via trail to Jackass Ginger, back to Hawaii Nature Center, loop endurance course, end at start/finish area. Two road crossings per 20 mile loop: 1. Nahuina/Tantalus Dr. 2. Moleka Trail/Manoa Cliffs Trail. Contact: PJ Salmonson 235-0577 Fax: 585-0166 | January 17, 2011 Monday 9:00AM Starts 12noon Ends | DR. MARTIN LUTHER KING JR. DAY PARADE sponsored by Martin Luther King Coalition. The event is expected to have 2,000 marchers, 100 vehicles, 20 floats, 6 bands. It will start at Ala Moana Park, to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave., end at Waikiki Shell Parking Lot in Queen Kapiolani Park. Contact: Patricia Anthony 384-4038 Fax: 672-4129 | - 30 - Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391. |