  You are here:  Main / Customer Services / Public Communications Division / 2012 / 06/14/12 Road Work Weekly Report
 

ROAD WORK WEEKLY REPORT

 

(Thu., June 14, 2012) − Scheduled road work for the week beginning June 17, 2012, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Rehabilitation of Streets, Phase 1 (aka IDIQ #2) – Honomanu St.  Paving Honomanu St.  Permanent striping, adjusting manhole and installing traffic detector loops to follow.

 

HAWAII KAI

Rehabilitation of Streets, Phase 1 (aka IDIQ #2) – Ainakoa Dr, Halekoa Dr, Hind Iuka Dr, Hao St, Kuliouou Rd, Keahole St, Kaluanui Rd, Kealahou St, Halemaumau St, Naio St, Kainui Dr.  Paving Halemaumau St.

 

HONOLULU

Ala Moana Blvd / Auahi Street Sewer Rehab, Phase 1:  Rehabilitation of 36" sewer line along Ala Moana Boulevard between Ahui Street and Ward Avenue

            (Estimated completion date, June 2012)

 

Houghtailing Street Area Sewer Rehabilitation:  Installation and rehabilitation of sewer lines and construction of new manholes along School Street.

            (Estimated completion date, continuing through June 2012)

 

Kalakaua Avenue Sewer Rehabilitation:  Installation of new 8" and 10" sewer line along Kalakaua Avenue between Philip Street and Kapiolani.

            (Estimated completion date, continuing through June 2012)

 

Kalihi/Nuuanu Sewer Rehabilitation Phase 1J (Area 8 – Pacific Heights)  Rehabilitation of approximately 1,400 linear feet of 6" and 2,300 linear feet of 8" sewer lines by cured-in-place pipe (CIPP) method.  A number of deteriorated manholes will also be repaired.  Star Road, Pacific Heights Road, Laniloa Road, Booth Road, and Hiolani Place will be affected.  Construction signs and police traffic control will be present.

            (Estimated completion date, February 2013)

 

King Street Reconstruction between River Street and Bethel Street, Chinatown:  Rehabilitation of sewer lines and select laterals, sewer manhole frame and cover replacement, excavation; Installation and backfill for new 6", 8" & 12" water lines, fire hydrants, valves, manholes; Installation and backfill for new 6" drain lines, inlets and manhole connections; Excavation and backfill for new gas lines; Demonish existing concrete and A.C. pavements to install new work and adjust manholes & valves boxes to grade. Work will include portions of River Street, Kekaulike Street, Maunakea Street, Smith Street, Nuuanu Street and Bethel Street where they intersect with King Street. Multiple lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, May 2013)

 

Miscellaneous Drainage Improvements at Various Locations – Lokahi Street (McCully)  Construct concrete drain inlets, concrete drain catch basins, connect to existing drain line, and install drain pipes.

            (Estimated Completion Date, continuing through June 2012)

 

Rehabilitation of Localized Streets, Phase 6A – McCully, Makiki, Moilili Areas  The work includes localized reconstruction of pavement and resurfacing of the streets indicated below; reconstruction of curbs, gutters, sidewalks and driveways are included; tree trimming, pruning and removal will be performed as necessary; post paving activities include permanent pavement markings and adjustment of utility manhole frames and covers to grade.  The affected roadways and limits of work are as follows:

 

Ahana Street, from Liona Street to Rycroft Street, Akala Lane, from King Street to Young Street, Akoko Street, from King Street to Young Street, Alder Street, from King Street to Kamaile Street, Algaroba Street, from Lokahi Street to 2128 Algaroba Street, Alohi Way, from Pensacola Street to Piikoi Street, Amana Street, from Kanunu Street to Makaloa Street, Artesian Street, from King Street to H-1 Freeway, Beverly Court, from Kinau Street to end, Bingham Street, from 360' East of Isenberg Street to Kaialiu Street, Birch Street, from King Street to Kamaile Street

 

Cedar Street, from Rycroft Street to makai end, Church Lane, from King Street to end, Citron Street, from Isenberg Street to ewa end, Coolidge Street, from Isenberg Street to King Street, Coyne Street, from 2121 Coyne Street to University Avenue, Cummins Street, from Queen Street to Waimanu Street, Elm Street, from Pensacola Street to Sheridan Street, Elsie Lane, from King Street to Young Street, Fern Street, from Kalakaua Avenue to Isenberg Street, Griffiths Street, from Beretania Street to Bingham Street, Hauoli Street, from Kapiolani Boulevard to King Street, Hausten Street, from Kapiolani Boulevard to King Street, Hihiwai Street, from University Avenue to Kamoku Street, Hoawa Lane, from King Street to Beretania Street, Hoawa Street, from Kapiolani Boulevard to Fern Street, Hoolai Street, from Pensacola Street to Piikoi Street, Hopaka Street, from Kona Street to Piikoi Street

 

Kaaha Street, from University Avenue to Kapiolani Boulevard, Kahakai Drive, from Kahakai Drive to Kahakai Drive, Kaheka Street, from Young Street to Kapiolani Boulevard, Kahoaloha Lane, from King Street to Nakookoo Street, Kaialiu Street, from Beretania Street to Bingham Street, Kalauokalani Way, from Makaloa Street to Kapiolani Boulevard, Kalei Road, from Kalele Road to end, Kalo Place, from Varsity Place to end, Kamoku Street, from Kaaha Street to Hihiwai Street, Kanunu Street, from Keeaumoku Street to Kalakaua Avenue, Kapaakea Lane, from King Street to end, Kawaiahao Street, from Ward Avenue to Kamakee Street, Kehena Place, from Old Waialea Road to end, Kemole Lane, from King Street to Beretania Street, Koali Road, from Old Waialae Avenue to mauka end, Kolo Place, from Varsity Place to end, Kuikahi Street, from Philip Street to Citron Street, Kuilei Street, from Kapaakea Lane to Waiaka Road

 

Lauiki Street, from Hihiwai Street to Kamoku Street, Lime Street, from Isenberg Street to end, Liona Street, from Cedar Street to Sheridan Street; and from Keeaumoku Street to Kaheka Street, Lokahi Street, from Citron Street to Algaroba Street, Lunalilo Street, from Makiki Street to Keeaumoku Street, Mahi Place, from Puaena Place to end, Mahiai Place, from Mahiai Street to end, Mahiai Street, from Date Street to Kapiolani Boulevard, Makahiki Way, from King Street to end, Makaloa Street, from Kalakaua Avenue to Piikoi Street, Makiki Street, from Beretania Street to H-1 Freeway deadend, Manalo Street, from Waiola Street to Citron Street, Matlock Avenue, from Piikoi Street to Keeaumoku Street, Maunawai Place, from Kapiolani Boulevard to end, Nahaku Place, from Mahiai Street to end,

 

Paani Street, from Kapiolani Boulevard to Waiola Street, Palm Drive, from King Street to Young Street, Pawaa Lane, from King Street to Beretania Street, Philip Street, from Kalakaua Avenue to 1633 Philip Street, Poha Lane, from Beretania Street to King Street, Poni Street, from Kanunu Street to Makaloa Street, Puaena Place, from University Avenue to end, Pumehana Street, from Kapiolani Boulevard to King Street, Punahou Street, from King Street to Philip Street, Rycroft Street, from Sheridan Street to Pensacola Street, TMK: 2-3-19:60, off of King Street between Kaheka Street and Kalakaua Avenue, Varsity Circle, from Varsity Place to Varsity Place, Varsity Place, from University Avenue to Varsity Circle, Victoria Street, from King Street to H-1 Freeway deadend, Villa Lane, from Beretania Street to Young Street, Waimanu Street, from Ward Avenue to 999 Waimanu Street; and from 1051 Waimanu Street to Piikoi Street, Waiola Street, from Makahiki Way to Manalo Street, Wiliwili Street, from King Street to Kapiolani Boulevard, Young Street, from Pensacola Street to Isenberg Street

 

Highway Structure Improvements, Pacific Heights Road Retaining Wall, Vicinity of 2210 Star Road

Removal and reconstruction of approximately 227 L.F. of concrete retaining wall with stone veneer facing; relocate joint utility poles and electrical lines for wall construction; replace existing electrical poles with new poles and lines; relocate existing streetlight fixtures on temporary poles for wall construction; install new streetlight fixtures on new poles; restore AC pavement fronting new wall;

restore pavement markings and markers; relocate existing signs and posts; provide traffic controls during working and non-working hours.

            (Estimated completion date, January 2013)

 

Bridge Rehabilitation at Various Locations I, FY 2009  Puowaina Drive Bridge over Auwaiolimu Street, Bridge No. 236  Repair of spalls in the concrete elements; repair of deteriorated CRM wall; replacement of concrete railing; strengthening concrete bridge sidewalks; shotcrete facing with soil/rock anchors; and miscellaneous repairs..

            (Estimated completion date, January 2013)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights.  The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street.

            (Estimated completion date, continuing through June 2012)

 

Rehabilitation of Streets, Unit 54 – Wilhelmina Rise, 13th Avenue to Matsonia Street  The work includes demolition and reconstruction of the existing PCC pavement and curbs identified on the plan.  Tree trimming, pruning and removal will be performed as necessary and as identified on the plan.  Adjustment of manholes and frames to grade as necessary; post paving activities include permanent pavement markings

 

            (Estimated Completion July 2012)

 

Wilhelmina Rise Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), lateral rehabilitation, and replacement of sewer lines by open trench.

            (Estimated completion date, continuing through June 2012)

 

KAILUA

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Aikahi Park.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal completed.  Kaneohe Bay Drive repair completed.

            (Estimated completion date, June 2013)

 

KANEOHE

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Kaneohe: Mokulele Dr and Kaneohe Bay Dr.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal at Mokulele Drive completed.

            (Estimated completion date, June 2013)

 

MAILI

Maili Stream Flood Control Improvements.  Scopt of work: remove and replace existing damaged concrete channel lining; remove and replace existing chain link fence.

            (Estimated completion date, December 2012)

 

MAKAKILO

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Honokai Hale.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal completed.

            (Estimated completion date, June 2013)

 

Rehabilitation of Localized Streets, Phase 7A – Aahualii Pl, Aahualii St, Ahikoe St, Ahiwa St, Akaawa Pl, Akaawa St, Akaula Pl, Akaula St, Ala Hoi St, Amaui Pl, Anipeahi Pl, Anipeahi St, Aoloko Pl, Aoloko St, Auwaea St, Awawa Pl, Awawa St, Elele Pl, Elele St, Hauone Pl, Hauone St, Helena St, Hoike Ply, Hoike Way, Hoina Pl, Hookeha Pl, Hookeha St, Hookomo St,

Hunekai Pl, Hunekai St, Ihi Pl, Kahea St, Kaiaulu Pl, Kaiaulu St, Kakoo Pl, Kaleo Pl, Kaleo Way, Kewai Pl, Kikaha St, Kinohi Pl, Kohea Pl, Kohea Way, Kohupono St, Kokole Pl, Kokole St, Kuamu St, Leiole St, Leipapa Way, Lihau St, Liolio Pl, Mehani Pl, Mehani St, Mekila St, Moaka St, Nenelea St, Newa Pl, Newa St, Nohohale St, Nohana Pl, Nohana St, Nohopaa St, Nohopono St, Oahi Pl, Oloa Pl, Painiu Pl, Palahia Pl, Palahia St, Palailai Pl, Palailai St, Panana St, Pilipono St, Pueonani St, Puliko Pl, Puliko St, Uahanai Pl, Uahanai St, Ualehei St, Uhiuala St, Ulele Pl, Umena St, Wainohia Pl, Wainohia St, Wainohia Way.  This Rehabilitation of Localized Streets project includes: cold planning; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas identified by the contractor and confirmed by the City; adjustment of utility manhole frames and covers, and street survey monument frame and covers; installation of pavement markers, striping and markings; installation of vehicle detector loops; locating existing manholes, valve boxes, monuments, etc. with GPS survey equipment and providing ArcGIS data files to City Dept. of Planning and Permitting in required data format.

 

NUUANU

Rehabilitation of Kimo Drive Bridge Over Nuuanu Stream, Bridge No. 260  Repair of spalls, concrete guardrails and bridge girders.

            (Estimated completion date, continuing through June 2012)

 

PEARL CITY

Rehabilitation of Streets, Phase 1 (aka IDIQ #2) – Oa St., Pahemo St, Lii Ipo St, Lokowai St, Lokowai Pl, Kanuku Pl, Kanuku St, Olepe Lp, Pahemo Pl, Hekaha St, Honomanu St, Pono St, Ponohale St, Ponohana Lp, Ponokaulike St, Ponokawila Pl, Ponokawila St and Kauhale St intersection.  Resurfacing Hekana St, Kanuku St, & Lii Ipo St.  Paving complete.  Adjusting manholes, permament striping and detector loops remaining.

            (Estimated completion date, continuing through June 2012)

 

PEARLRIDGE

Rehabilitation of Streets, Unit 51 – Moanalua Road, Kaahumanu Street, Hoomaemae Street, and Hoomalu Street:  Cold planing; excavation of existing asphalt concrete pavements; resurfacing and reconstruction of asphalt concrete pavements; portland cement concrete pavements; reconstruction of existing concrete curbs and/or gutters; arboricultural work; repair of catch basins; adjustment of utility manhole frames and covers; installation of pavement markings; vehicle detector loop installation; and traffic control.

            (Estimated completion date, July 2012)

 

SALT LAKE

Emergency Repairs to Mahiole Street Bridge over Manaiki Stream, Bridge No. 145:  Repair of spall/delamination.

            (Estimated completion date, August 2012)

 

WAHIAWA

Rehabilitation of Streets, Unit 58 – California Avenue (Kamehameha Highway to mauka end of California Avenue):  Cold planing; resurfacing and reconstruction of asphalt concrete pavement; adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, berms, sidewalks and Driveways; and construction of concrete and asphalt concrete bus pads.

            (Estimated completion date, continuing through June 2012)

 

WAIKIKI

Beachwalk Force Main Phase I:  2 Staging pits to be constructed along Ala Wai Boulevard from Kalakaua towards Ala Moana Boulevard for the microtunneling installation of new sewer line.

            (Estimated completion date, continuing through April 2012)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

June 17, 2012 Sunday
6:00AM Starts
10:00AM Ends

BIKEFACTORY NORTH SHORE TRIATHLON sponsored by North Shore Triathlon/BikeFactory.  The event is expected to have 300 triathletes. SWIM-400meters: It will start at Mokuleia Beach Park out and back course ending on beach near transition area.  BIKE-10.3m: Mokuleia transition area, to Farrington Hwy., west on Farrington Hwy., to Kahui Rd., to Kanoulu St., to Kane Pl., to Kanoena Pl.-to Kanoulu St., to Farrington Hwy., west on Farrington Hwy,  back to Mokuleia Beach Park transition area.  RUN-3m: From Mokuleia Beach Park transition area,  right onto Farrington Hwy-west on Farrington Hwy-turnaround on Farrington Hwy-east on Farrington Hwy-finish at Mokuleia Beach Park.  Contact: Chris Gardner 372-8885, Fax:  485-0101, E-mail: northshoretriathlon@gmail.com

 

June 23, 2012 Saturday
5:00PM Starts
10:00PM End
s

MURPHY'S HAWAII CHILDREN'S CANCER FOUNDATION BLOCK PARTY sponsored by Murphy's Bar & Grill/HCCF. The event is expected to have 200+ participants.  The event will close MERCHANT ST., from Nuuanu Ave. to Bethel St. from 7 am for setup.  Contact:  Don Murphy 531-0422, Fax:  533-4943, E-mail:  murphysbarandgrill@hawaii.rr.com

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391.

Wednesday, June 13, 2012

City and County of Honolulu News

 
Official website of the City and County of Honolulu
 
  You are here:  Main / Customer Services / Public Communications Division / 2012 / 06/13/13 New Waikiki Sewer Lines Nearing Completion
 

NEW WAIKIKI SEWER LINES NEARING COMPLETION

(Wed., June 13, 2012)—Mayor Peter Carlisle today announced that the Beachwalk Force Main sewer project in Waikiki is nearing completion. As the portion of the new permanent force main that connects the Beachwalk Wastewater Pump Station in Waikiki to the temporary bypass line on the mauka side of the Ala Wai Canal has been completed, two smaller 28-inch temporary pipes will be floated to the canal's surface and removed this week. The two smaller pipes were installed in and across the canal following the massive 2006 sewage spill. 

"This project is very important for protecting our environment and public health in Waikiki," Carlisle said. "Investing wisely in our infrastructure is the key to preparing for our future."

The Beachwalk Force Main project includes the installation of 5,800 feet of new, 72-inch diameter pipe running from the Ala Wai Elementary School, near the makai end of University Avenue, to the Moana Park Wastewater Pump Station at the Atkinson Street entrance to Ala Moana Beach Park. 

The new pipe consists of five segments, four of which have now been installed. Specialized pipe for the final segment is slated to arrive this week, and the entire project is expected to be completed by early 2013.

The two 28-inch diameter temporary pipes that will be removed from the canal this week are separate from the 48-inch diameter temporary pipe that became visible when a portion floated to the surface of the canal last month. That temporary pipe was re-submerged and will be removed after the final segment of the permanent new pipe is installed.

Once the entire $46 million project is complete, two reliable systems will transport wastewater from Waikiki: the existing 48-inch diameter pipe running beneath Ala Wai Boulevard; and the new 72-inch diameter pipe running beneath Ala Wai Park, crossing the canal and under Ala Wai Blvd to the pump station. For more information, go to www.beachwalkforcemain.com .

The City has also begun a separate project that will rehabilitate 6,000 feet of sewer lines in Waikiki along Kuhio Avenue between Namahana Street and Liliuokalani Avenue. The $5.7 million project is expected to be completed in the summer of 2013. For more information, go to www.waikikisewer.com  

-30-

Media contact: Louise Kim McCoy, Mayor's Office, 768-7798.

 

Tuesday, June 12, 2012

City and County of Honolulu News

06/12/2012 Summer Fun Programs "Get Active, Get Fit", Official Web Site for The City and County of Honolulu
 
Official website of the City and County of Honolulu
 
  You are here:  Main / Customer Services / Public Communications Division / 2012 / 06/12/2012 Summer Fun Programs "Get Active, Get Fit"
 

FOR IMMEDIATE RELEASE                                                                                       June 12, 2012

 

SUMMER FUN PROGRAMS  "GET ACTIVE, GET FIT"

 

(Tue., June 12, 2012)—The Department of Parks and Recreation's popular Summer Fun Program, which attracts more than 9,000 youths on Oahu annually, has just announced it will be implementing a healthier "Get Active, Get Fit…E Oni Kakou" theme this summer.

 

            In an effort to help combat the obesity epidemic in Honolulu, Parks and Recreation will be offering healthy beverage alternatives in their vending machines.  Parks staff has replaced the sugar-sweetened beverages and sodas with 100% fruit juices and water in all their drink dispensers at the 60 Summer Fun Program sites. Children participating at these sites will also be encouraged to take the "Soda-Free Summer Challenge," a pledge to abstain from drinking sugar-sweetened beverages for the duration of the Summer Fun Program.

            In addition, Parks and Recreation will continue to promote physical activity in the Summer Fun program as they have done in previous years.  This year, current and former NFL players will visit selected summer fun sites on Oahu and will be promoting the NFL Play60 movement for active generations.  Players will interact with summer fun keiki through physical activities and Play60 events like the Punt, Pass, and Kick Competition.

 

            In Hawaii, almost one in three children kindergarten are overweight or obese, and the percentage of high school students who are obese increased 26% from 1999 to 2011. Almost one in five high school students report consuming at least one sugary drink per day, accounting for about 10% of their overall diet. Additionally, four out of five high school students fail to meet national recommendations for physical activity. Changing our environment to make healthy food and beverage options more accessible and increasing opportunities for physical activity are critical steps in reversing this trend.    

 

            "It's more than changing drinks.  It's really altering children's lifestyles and habits.  By making healthy foods and beverages available, accessible, and affordable, and incorporating different physical activities into the program, we hope to influence healthy choices," said Mayor Peter Carlisle.  "More than one-third of adults and close to one-fifth of children and adolescents in the United States are obese, accelerating to epidemic proportions.  We have to work together to effect change.  Success requires action from all of us," added Carlisle  

 

           The State Department of Health is partnering with the City in this initiative.  According to Director of Health Loretta J. Fuddy, these positive changes are another exciting step toward improving the health of our keiki.  "This is a great example of government being proactive and making healthy food choices, and beverages accessible at places where our children learn and play, and families and communities gather," said Fuddy.

 

           The Department of Parks and Recreation offers seven weeks of Summer Fun at 60 sites throughout the island of Oahu.  Children enjoy a wide variety of arts and crafts, sports and games, excursions, and special events.  There is a $25 registration fee, which is waived for eligible families, and up to $75 for activity fees.

 

           For more information of summer fun programs, contact the Department of Parks and Recreation,

768-3001.   

 

-30-

 

 

Media Contact:  Deputy Director Al Tufono, 768-3002

 

This message has been brought to you by the City and County of Honolulu List Server application to update your settings visit: YOUR ACCOUNT PAGE

City and County of Honolulu News

 
Official website of the City and County of Honolulu
 
  You are here:  Main / Customer Services / Public Communications Division / 2012 / 06/12/12 Traffic Advisory: Lane Closures for Archaeological Survey in Urban Honolulu
 

TRAFFIC ADVISORY: LANE CLOSURES

FOR ARCHAEOLOGICAL SURVEY WORK IN URBAN HONOLULU

 

(Tue., June 12, 2012) − The Honolulu Authority for Rapid Transportation (HART) wants to inform drivers that archaeological survey work continues next week in the urban Honolulu area for the rail transit project.

 

Motorists are advised of lane closures related to the survey work being conducted in the Airport, Kalihi, downtown Honolulu, and Kakaako areas.

 

Work will require lane closures during non-peak traffic hours, including possible night work in approved areas.

 

            For the safety of both the work crews and motorists, the public is advised to proceed with caution through these areas. Drivers should anticipate possible traffic delays or use alternate routes during work hours, and provide a safe distance between themselves and the construction workers and equipment.

 

            Work for the week of Sunday, June 10, through Saturday, June 16, will take place at the following locations:

·    Nimitz Highway between River Street and Halekauwila Street from 8:30 a.m. to 3 p.m.

·    Kamehameha Highway between Middle Street and Laumaka Street from 7:30 p.m. to 4 a.m.

 

            The City is conducting the archaeological survey work along the urban Honolulu section of the Honolulu rail transit route to identify potential archaeological, historical and cultural resources. The archaeological work will aid rail project staff in their design of the elevated rail guideway.

 

            Trenching work will take place at various locations along the Honolulu rail route between Middle Street in Kalihi and Ala Moana Center. Contractors Cultural Surveys Hawaii Inc. and Royal Contracting Co. are conducting the fieldwork.

 

            The survey work will be completed before rail construction begins in the urban Honolulu area, as specified under the rail project's programmatic agreement relating to cultural and historic resources.

 

            For updates on construction work days and times, visit the project website at www.honolulutransit.org or contact our hotline at 566-2299.

 

- 30 -

 

Media Contact: Scott Ishikawa, (808) 768-6172, cell: (808) 227-2350.