ROAD WORK WEEKLY REPORT (Thurs., February 16, 2012) − Scheduled road work for the week beginning February 19, 2012, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below. Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted. HAWAII KAI Rehabilitation of Streets, Phase 1 (aka IDIQ #2) Ainakoa Dr, Halekoa Dr, Hind Iuka Dr, Hao St, Kuliouou Rd, Keahole St, Kaluanui Rd, Kealahou St, Halemaumau St, Naio St, Kainui Dr. Paving Halekoa Dr, Kealahou and Hao St. Adjusting manholes and permanent striping to follow. Repair Kalapaki Street Drainage Ditch Wall Vicinity of 977 Kalapaki Street: Removal and disposal of existing concrete ditch wall and slab. Construction of new reinforced concrete ditch wall and slab. Installation of new chain link fence. Repair crack and spalled concrete on existing wall. (Estimated completion date, continuing through February 2012) Kipu Ditch Storm Drainage Improvements Vincinity of Kamiloiki Community Park and Kamiloiki Elementary School. Reconstruction of existing drainage ditch; spall and delamination repairs along portion of drainage ditch; installation of new chain link fence; planting of new trees and biobarrier installation; tree and root pruning and removal of trees, shrubs and hedges for new drainage ditch. (Estimated completion date, March 2012) Curb Ramps at Various Locations, FY 2010 (A) Lunalilo Home Road between Hawaii Kai Dr. and Kalanipuu St.: Construction of new curb ramps, sidewalks and A.C. pavement transition. Relocation of existing regulatory/street signs. Adjustment of utility boxes. Installation of pavement striping, markings and markers. (Estimated completion date, continuing through February 2012) HONOLULU Houghtailing Street Area Sewer Rehabilitation: Installation and rehabilitation of sewer lines and construction of new manholes along School Street. (Estimated completion date, continuing through February 2012) Kalakaua Avenue Sewer Rehabilitation: Installation of new 8" and 10" sewer line along Kalakaua Avenue between Philip Street and Kapiolani. (Estimated completion date, continuing through February 2012) Kalihi/Nuuanu Sewer Rehabilitation Phase 1J (Area 8 Pacific Heights) Rehabilitation of approximately 1,400 linear feet of 6" and 2,300 linear feet of 8" sewer lines by cured-in-place pipe (CIPP) method. A number of deteriorated manholes will also be repaired. Star Road, Pacific Heights Road, Laniloa Road, Booth Road, and Hiolani Place will be affected. Construction signs and police traffic control will be present. (Estimated completion date, February 2013) Rehabilitation of Streets, Phase 1 (aka IDIQ #2) Kanewai St, Kaluawaa St, Kamakini St, Waiomao Rd, 8th Ave, 9th Ave, Paalea St, Kalua Rd, Mahana St, Kiwila St. Finished paving Kanewai St, Kaluawaa St and Kamakini St. Adjusting manholes, permanent striping and detector loops to follow. King Street Reconstruction between River Street and Bethel Street, Chinatown: Rehabilitation of sewer lines and select laterals, sewer manhole frame and cover replacement, excavation; Installation and backfill for new 6", 8" & 12" water lines, fire hydrants, valves, manholes; Installation and backfill for new 6" drain lines, inlets and manhole connections; Excavation and backfill for new gas lines; Demonish existing concrete and A.C. pavements to install new work and adjust manholes & valves boxes to grade. Work will include portions of River Street, Kekaulike Street, Maunakea Street, Smith Street, Nuuanu Street and Bethel Street where they intersect with King Street. Multiple lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m. (Estimated completion date, May 2013) Miscellaneous Drainage Improvements at Various Locations Lokahi Street (McCully) Construct concrete drain inlets, concrete drain catch basins, connect to existing drain line, and install drain pipes. (Estimated Completion Date, continuing through February 2012) Mokauea Street Improvements between North King Street and Dillingham Boulevard: Reconstruction concrete curbs and gutters, driveway and some sidewalks; construct new curb ramps; reconstruct and resurface asphalt roadway. Reconstruction of shallow drain line across Akina Street added. Post paving activities include installation of permanent pavement markings, adjust utilities to finish grade, and re-install traffic loop detectors. (Estimated Completion continuing through February 2012) Sewer Manhole and Pipe Rehabilitation at Various Locations Phase 2: Various manhole rehabilitation along Nimitz Highway between Pacific Street and Sumner Street. (Estimated completion date, continuing through February 2012) Curb Ramps at Various Locations, FY 2009 (B), Palolo and Kaimuki: Construction of new curb ramps, sidewalks and A.C. transition. Relocation of existing regulatory/street signs. Installation of pavement striping, markings and markers. (Estimated completion date, continuing through February 2012) Queen Street Roadway Improvements Queen Street, Diamend Head side of Queen Street and Punchbowl Street intersection: Demolition and reconstruction of existing concrete bus pad, curb ramps, sidewalk, curb and gutter, and thru gutter. Cold planing, resurfacing and reconstruction of A.C. pavement. Adjustment of utility manhole frames and covers. Installation of pavement striping, markings and markers. (Estimated completion date, continuing through February 2012) Saint Louis Heights Sewer Rehabilitation: Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights. The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street. (Estimated completion date, continuing through February 2012) Wilhelmina Rise Sewer Rehabilitation: Installation of cured in place pipe (CIPP), lateral rehabilitation, and replacement of sewer lines by open trench. (Estimated completion date, continuing through February 2012) KAILUA Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Aikahi Park. The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Slurry seal completed. Kaneohe Bay Drive repair completed. (Estimated completion date, June 2013) Curb Ramps at Various Locations, FY 2010 (A) Hele St./Liku St., Hele St./Mowai St., Hele St./Kina St., Kina St./Loho St., Kina St./Kupau St., Apokula St./Apokula Pl., Apokula St./Kupau St., Kuloaa Pl./Kupau St., Kupau St./Kupau Pl., Hele St./Loho St., and Hele St./Mapuana St.: Construction of new curb ramps, sidewalks and A.C. pavement transition. Relocation of existing regulatory/street signs. Adjustment of utility boxes. Installation of pavement striping, markings and markers. (Estimated completion date, continuing through February 2012) KANEOHE Flood Control Improvements at Various Locations FY 2008 Kaneohe, Kailua & Waipio: Demolish and reconstruct new concrete and asphalt concrete ramps and driveways. Repair existing concrete ditch and adjust utility frames, covers and boxes to finish grade. (Estimated completion date, continuing through February 2012) Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Kaneohe: Mokulele Dr and Kaneohe Bay Dr. The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Slurry seal at Mokulele Drive completed. (Estimated completion date, June 2013) Miscellaneous Storm Drainage Improvements at Wailele Road Outlet: Construction of a new 6' x 5' box culvert, drop manhole, impact-stilling basin, and concrete pavement; waterline relocation; installation of 6' and 4' chain link fencing and gates, and metal guard rail. (Estimated completion date, February 2012) MAKAKILO Curb Ramps at Various Locations, FY 2010 (A) Anipeahi St./Palailai St.: Construction of new curb ramps, sidewalks and A.C. pavement transition. Relocation of existing regulatory/street signs. Adjustment of utility boxes. Installation of pavement striping, markings and markers. (Estimated completion date, continuing through February 2012) Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 Honokai Hale. The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops. Slurry seal completed. (Estimated completion date, June 2013) NUUANU Rehabilitation of Kimo Drive Bridge Over Nuuanu Stream, Bridge No. 260 Repair of spalls, concrete guardrails and bridge girders. (Estimated completion date, continuing through February 2012) PEARL CITY Rehabilitation of Streets, Phase 1 (aka IDIQ #2) Oa St., Pahemo St, Lii Ipo St, Lokowai St, Lokowai Pl, Kanuku Pl, Kanuku St, Olepe Lp, Pahemo Pl, Hekaha St, Honomanu St, Pono St, Ponohale St, Ponohana Lp, Ponokaulike St, Ponokawila Pl, Ponokawila St and Kauhale St intersection. Resurfacing Hekana St, Kanuku St, & Lii Ipo St (Estimated completion date, May 2012) PEARLRIDGE Rehabilitation of Streets, Unit 51 Moanalua Road, Kaahumanu Street, Hoomaemae Street, and Hoomalu Street: Cold planing; excavation of existing asphalt concrete pavements; resurfacing and reconstruction of asphalt concrete pavements; portland cement concrete pavements; reconstruction of existing concrete curbs and/or gutters; arboricultural work; repair of catch basins; adjustment of utility manhole frames and covers; installation of pavement markings; vehicle detector loop installation; and traffic control. (Estimated completion date, July 2012) SALT LAKE Rehabilitation of Streets, Phase 1 (aka IDIQ #2) Ala Mahamoe St, Ala Lilikoi St, Ala Napunani St, Salt Lake Blvd, Kanewai St, Kaluawaa St, Kamakini St, Waiomao Rd, Ala Alii St, Anapa St, Haloa Sr, Halupa St, Holapa St, Kukila Pl, Kukila St, Laakea Pl, Laakea St, Lehia St, Loina Pl, Luapele Dr, Luapele Pl, Mahie Pl, Mahie St, Molehu Dr, Molina St, Naulu Pl, Olaloa St, Olino St, Opua St, Palahinu Pl, Piikea Pl, Piikea St, Puanakau St, Ukali St, Uila St, Wawe Pl, Kahikolu Pl, Kahikolu Way, Likini St, Makaala St, Manuwa Dr, Miko St, Pakini St, Ukana St, Wanaka St. Finished paving Salt Lake area. Adjusting manholes, placing permanent striping and detector loops in various streets of Halawa and Salt Lake Blvd remain. WAHIAWA Rehabilitation of Streets, Unit 58 California Avenue (Kamehameha Highway to mauka end of California Avenue): Cold planing; resurfacing and reconstruction of asphalt concrete pavement; adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, berms, sidewalks and Driveways; and construction of concrete and asphalt concrete bus pads. (Estimated completion date, March 2012) WAIANAE Mailiili Stream Flood Control Improvements Near Halona Road and Puuhulu Road: Removal and reconstruction of damaged concrete channel lining, construction of new channel access ramp near Halona Road Bridge, and construction of overflow side-drains on the channel banks. (Estimated completion date, continuing through February 2012) WAIKIKI Beachwalk Force Main Phase I: 2 Staging pits to be constructed along Ala Wai Boulevard from Kalakaua towards Ala Moana Boulevard for the microtunneling installation of new sewer line. (Estimated completion date, continuing through February 2012) Curb Ramps at Various Locations, FY 2010 (A) Paoa Place (Hilton Hawaiian Village Third Driveway): Construction of new curb ramp and A.C. pavement transition. (Estimated completion date, continuing through February 2012) PARADES, WALKS, RACES AND OTHER STREET CLOSURES February 20, 2012 Monday 6:45AM Starts 11:00AM Ends | GREAT ALOHA RUN sponsored by Great Aloha Run/Carole Kai Charities. The event is expected to have 22,000+ runners. It will start on Nimitz Hwy. at Nuuanu Ave., to Nimitz Hwy., ewa bound, to Kamehameha Hwy then under the H-1 viaduct, to Kamehameha Hwy., to Aloha Stadium service road into the main gate of Aloha Stadium, to finish in the north end zone of Aloha Stadium. Contact: Carol Jaxon 528-7388, Fax: 528-7392 For more info, visit their website: http://www.greataloharun.com/ | February 21, 2012 Tuesday 6:00PM Starts 11:00PM Ends | NUUANU MARDI GRAS STREET FESTIVAL sponsored by Arts District Merchant Association. The event is expected to have 7,000+ participants. The event will close 1)NUUANU AVE., all traffic lanes/sidewalk areas, from Chaplain Ln to King St. 2)PAUAHI ST., all traffic lanes/sidewalk areas, from Smith St. to Bethel St. 3)HOTEL ST., all traffic lanes/sidewalk areas, from Smith St. to Bethel St. 4)SMITH ST., all traffic lanes/sidewalk areas, from Hotel St to Pauahi St. Contact: Eric Walden 271-3094, or Ed Korybski 398-7990, For more info, visit their website: http//www.artsdistricthonolulu.com | February 22, 2012 Wednesday 8:30AM Starts 10:00AM Ends | WAIPAHU ELEMENTARY SCHOOL DRUG FREE WALK sponsored by Waipahu Elem. School. The event is expected to have 1,300 participants. It will start at Waipahu Elem. School on Waikele Rd., to Pupupuhi St., to Pupukahi St., to Farrington Hwy., to Pupupuhi St., to Waikele Rd., to finish at Waipahu Elem. School. Contact Roschelle Kalili 675-0150 ext. 305, Fax: 675-0121, E-mail: rochelle_kalili@notes.k12.hi.us | February 26, 2012 Sunday 7:00AM Starts 10:00AM Ends | MAKAHA BEACH TIME TRIAL sponsored by Cambiamento d'Andaturo. The event is expected to have 75 participants. It will start at Kaena Point State Park, to Farrington Hwy., turnaround at Makaha beach, to loop at end at Kaena Pt. State Park. Contact: David Lum 429-9475, Fax: 839-2094, E-mail: rhombus01@msn.com | - 30 - Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391. |