April 25, 2014

 

Road Work Weekly Report

 

Scheduled road work for the week beginning April 27 for the Department of Design and Construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below. Road work is normally done between the hours of 8:30 a.m. and 3:30 p.m. unless otherwise noted.

 

EWA BEACH

Rehabilitation of Localized Streets, Phase 7B – Ewa Village

Alaiki St, Ala Loa St, Alana St, Alanui Mauka Pl, Alanui Mauka St, Auwaha St, Bond St, Bryan St, Burke St, Ekemauu St, Halolani St, Hapaiko St, Garton St, Halemano St, Hapua St, Hei Pl, Hookahe Pl, Hoopio St, Hulili St, Imelda St, Kamahoi St, Karayan St, Kikoo St, Kuali St, Kuapuu St, Kupeleko Pl, Kuuwelu Pl, Lako St, Lauo St, Lehu St, Luahine St, Luluka St, Lunanui St, Mahamoe St, Malako St, Maliko St, Miula St, Nale St, Niulelo Pl, Oha St, Olehala St, Oohao St, Orrick St, Paaniana St, Paeheulu St, Paekii St, Paeko St, Pahe St, Paheahea St, Pahika St, Park Row, Pepper Row, Pihi St, Pipeline St, Pohakulepo St, Pualoalo Pl, Pualu St, Puhiko St, Punako St, Puuhala St, Sisal St, Tenney St, Uluhui St and Wili St.

 

Project includes: cold planning; resurfacing of asphalt concrete pavements; reconstruction of failed asphalt concrete pavement areas identified by the contractor and confirmed by the City; adjustment of utility manhole frames and covers, and street survey monument frame and covers; installation of pavement markers, striping and markings; installation of vehicle detector loops; locating existing manholes, valve boxes, monuments, etc. with GPS survey equipment and providing ArcGIS data files to City Dept. of Planning and Permitting in required data format.

Paving complete. Adjusting manholes and placing permanent striping on various streets is on going.  Varona Village area will be included.

 

Rehabilitation Of Streets – Renton Road (Between Kapolei Parkway and Asing Park)

The project involves (1) road reconstruction and resurfacing; (2) curb, gutter and catch basin reconstruction; (3) pavement striping, markings and markers; (4) tree trimming and root pruning; adjustment of manholes and utility boxes to new finish grade; (5) installation of speed bumps.

            (Estimated completion date, continuing through April 2014)

 

HAWAII KAI

Hanapepe Loop Drain Outfall Improvements:  Demolish and reconstruct existing concrete outlet structure, provide BMP devices, restore area to pre-construction;

            (Estimated completion date, September 2014)

 

Rehabilitation of Streets, Unit 25 (Lunalilo Home Road & Mariners Cove):  The work includes localized reconstruction of pavement and resurfacing of the streets indicated below; reconstruction of identified curbs and gutters are included; tree trimming, pruning and removal will be performed as necessary under the guidance of qualified arborist; post paving activities include permanent pavement markings and adjustment of utility manhole frames and covers to grade.  Mariners Cove and Portlock paving complete; and continue constructing concrete bus pads along Lunalilo Home Road; continue paving between Wailua Street and Hawaii Kai Drive.

The affected roadways and limits of work are as follows:

 

Wailua Street from Hawaii Kai Drive to Lunalilo Home Road, Lunalilo Home Road from Portlock Road to Wainiha Street – mauka intersection, Hawaii Kai Drive from Lunalilo Home Road to Kamilo Street, Kamilo Street from Hawaii Kai Drive to Hawaii Kai Drive, Niumalu Loop from Kamilo Street to Kamilo Street, Hoopii Place from Niumalu Loop to End, Kukuii Street from Kamilo Street to Niumalu Loop, Naakea Street from Kamilo Street to Kamilo Street, Olohena Street from Niumalu Loop to Naakea Street, Halaula Place from Kamilo Street to End, Naakea Place from Naakea Street to End, Kokomo Place from Kamilo Street to End, Opoi Street from Niumalu Loop to Kamilo Street, Paoo Street from Niumalu Loop to Kamilo Street.

            (Estimated completion date, continuing through April 2014)

 

Rehabilitation of Streets, Unit 71 (Lunalilo Home Road Kalanianaole Highway to Kealahou Street: The work includes reconstruction and resurfacing of the asphalt roadway; reconstruction of identified curbs and gutters; tree trimming, pruning and removal will be performed as necessary under the guidance of qualified arborist; post paving activities include permanent pavement markings; adjustment of utility manhole frames and covers to grade and reinstallation of traffic loop detectors.

            (Estimated completion date, September 2014)

 

HONOLULU

Airport Sewer Rehabilitation / Reconstruction, Phase 2  CIPP rehabilitation of 36" sewer lines along Aolele Street, from Rodgers Blvd to Lagoon Drive.

            (Estimated completion date, continuing through December 2014)

 

Ala Moana Blvd./Auahi Street Sewer Rehab, Phase 2  Rehabilitation of approx. 1,980 LF of existing 6'x6' box sewer along Auahi Street from Kamani Street to Keawe Street including relocation of existing waterlines;  installation of 210LF of new 6" sewer line at 711 Ala Moana Blvd.;  and rehabilitation of existing concrete manholes including abandonment of existing 36" sewer line along Ala Moana Blvd.

(Estimated completion of all other work at June 2014)

 

Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program: Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves.  Re-grade swale and adjust existing D.I. frame / cover to provide positive runoff flow into existing Drain system. Reconstruct concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams. Restore existing chain link fence at outlet area. At the intersection of Ahua Street and Awaawaloa Street, provide permanent concrete plug in existing 24" DL.

            (Estimated completion, continuing through April 2014)

 

Palani Avenue Drainage Improvements  Installation of drainage pipes, drainage structures, and check valves within Date Street and Palani Avenue. 

            (Estimated completion date, continuing through April 2014)

 

Rock Slide Potential Inspection and Mitigative Improvements along Prospect Street

The work includes clearing and grubbing ; excavating ; installing rockfall impact barrier systems ; installing concrete barriers ; installing draped wire mesh systems ; traffic control ; and tree removal.

            (Estimated completion date, December 2014)

 

Rehabilitation of Saint Louis Drive Bridge, Bridge No. 334:  Repair of concrete delamination, spalls and cracks on the existing bridge structure; repair of expansion joints; installation of painted steel guardrail extension; and miscellaneous repairs.

            (Estimated completion date, continuing through April 2014)

 

Wilder Avenue and Metcalf Street Sewer Rehabilitation

Rehabilitation work of approximately 640 feet of 6" sewer along Wilder Avenue, between Metcalf Street and Evelyn Lane.  One lane closure westbound Monday through Friday 8:30am – 3:30pm.

            (Estimated completion date, continuing through April 2014)

 

KAILUA

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Aikahi Park.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal completed.  Kaneohe Bay Drive repair completed.

            (Estimated completion date, continuing through April 2014)

 

KAIMUKI

Rehabilitation Of Streets, Unit 57 – Kaimuki area

The work includes reconstruction of pavement and resurfacing of streets; reconstruction of curbs, gutters, sidewalks, driveways and bus pads; tree trimming, root pruning and tree removal as necessary; pavement markings and markers, installation of vehicular detector loops, adjustment of street monuments to new finish grade, and adjustment / reconstruction of utility manhole / valve box frames and covers to new finish grade.

 

The affected roadways and limits of work are as follows:  Waialae Avenue from Kapahulu Avenue to 17th Avenue; 5th Avenue from Waialae Avenue to Harding Avenue; 6th Avenue from Harding Avenue to Pahoa Avenue; 7th Avenue from Waialae Avenue to Pahoa Avenue; 8th Avenue from Waialae Avenue to H-1 Freeway; 9th Avenue from Waialae Avenue to H-1 Freeway; 10th Avenue section crossing H-1 Freeway; 11th Avenue from Waialae Avenue to Harding Avenue; 12th Avenue from Waialae Avenue to H-1 Freeway; 13th Avenue from Keanu Street to Claudine Street; 14th Avenue from Waialae Avenue to Keanu Street; 15th Avenue from Waialae Avenue to Noeau Street; 16th Avenue from Waialae Avenue to end (mauka side); 17th Avenue H-1 Freeway to Noeau Street; and Moi Way, Anuhea Place, Ekaha Avenue, Hoku Avenue, Keanu Street, Noeau Street, Claudine Street, Koko Head Drive.

            (Estimated completion date, June 2014)

 

MAILI

Maili Stream Access Ramp  Scopt of work:  Installation of an approximately 80-foot long concrete access ramp and retaining walls to provide access to the Maili channel east of Maliona Street

            (Estimated completion date, September 2014)

 

MAPUNAPUNA

Seismic Retrofit of City Bridge, Kikowaena Street Bridge, Bridge No. 102

The project includes seismic retrofit of Kikowaena Street Bridge (Bridge No. 102). Work includes construction of concrete members, traffic control measures, restoration of pavement and pavement markings, and erosion control work.  Night work: hours 8:00 pm to 4:30 am (Sun - Thu); bridge closed to traffic.

            (Estimated completion date, May 2014)

 

MILILANI

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Aelike Pl, Aelike St, Ahahuina Pl, Ahea Pl, Ahea St, Ahikao St, Ahohui St, Ahokele St, Ahulili St, Ailona St, Ainakuai Pl, Ainamakua Dr, Ainana Pl, Ainana Way, Akaluli St, Akeake St, Alakaina St, Alaoki Pl, Alaoki St, Alaume Pl, Alaume St, Alenale Pl, Anuanu St, Aoakua St, Auina Pl, Auina St, Haakualiki Pl, Haakualiki St, Haike Pl, Hakala St, Halehaku Pl, Halekua St, Haike Pl, Hakala St, Halehaku Pl, Halekua St, Halelau Pl, Haloku Pl, Haloku St, Hoahiahi Pl, Hoahui St, Hoailona Pl, Hoailona St, Hoakua Pl, Hoaluhi Pl, Hoani Pl, Holokia Pl, Hololani St, Hololea St, Hookaau St, Hookanahe St, Hookowa Pl, Hookowa St, Hookupu St, Hoomua St, Hooni Pl, Hoonui Pl, Iimi Pl, Kaapeha St, Kahanui St, Kahele Pl, Kahele St, Kahonua St, Kahualea St, Kailewa St, Kamalino St, Kanae St, Koliliko St, Konaku St, Koolua Pl, Koolua Way, Kopalani St, Kowa St, Kuahaua Pl, Kuahewa St, Kuanoni Pl, Kuanoni Way, Kuaoa St, Kuauli St, Kuauna Pl, Kuena St, Kuhea St, Kuikepa Pl, Kuinehe Pl, Kukini Pl, Lahui Pl, Lahui St, Lapaiki St, Lauae St, Lehiwa Dr, Liho St, Lilii Pl, Luaehu Pl, Luaehu St, Makaikai Pl, Makaikai St, Malielie Pl, Malielie St, Meahou St, Meanui St, Milia Pl, Milia St, Mua Pl, Naaualii Pl, Ohi St, Oliliko St, Paea St, Paeli Pl, Pakau St, Puakai Pl, Puneki Pl, Puneki St, Puneki Way, Puulu St, Ulahea Pl, Ulahea St, Ululele Pl:

 

The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; arboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.

 

Slurry sealing Haloku St, Ahulili St, Kukini Pl, Kuinehe Pl, Ahokele St and Kuaoa St. Permanent striping to follow.

            (Estimated completion date, continuing through April 2014)

 

Rehabilitation of Streets, Unit 68 (Meheula Parkway and Anania Drive):  The work includes reconstruction and resurfacing of the asphalt roadway; reconstruction of identified curbs and gutters; tree trimming, pruning and removal will be performed as necessary under the guidance of qualified arborist; post paving activities include permanent pavement markings; adjustment of utility manhole frames and covers to grade and reinstallation of traffic loop detectors.

            (Estimated completion date, December 2014)

 

NUUANU

Rehabilitation of Nuuanu Avenue Bridge, Bridge No. 251:  Repair to concrete spalls and delaminations; and increase guardrail height.

            (Estimated completion date April 2014)

 

PALOLO

Kuahea Street Interim Repair, Vicinity of 2395 Kuahea Street: Removing and replacing existing asphalt concrete pavement, extending excavation about 4.5 feet below pavement surface and backfilling with geogrid reinforced soil mat and light weight geofoam structural material, relocating existing gas, water, and sewer lines with new manholes and/or thrust blocks, and installing 6-inch diameter underdrain.

            (Estimated completion date, April 2014)

 

PUPUKEA

Pupukea Road Rockfall Mitigation Phase II:  The work consists of clearing vegetation within the project limits, scaling boulders and unstable rocks or installing rock dowels (where appropriate), applying shotcrete (where required), installing rock fall protection fences, drapery system and landscaping. One traffic lane will be closed during work hours at Pupukea Road with police performing traffic control duties.

(Estimated completion date, September 2014)

 

WAIAU

Waiau Area Sewer Rehabilitation/Reconstruction – Kuleana Place, Kaulike Drive, Kauhihau Place, and Hile Place:  Excavation and replacement of approx. 728LF of 8" sewer main including reconnection of existing sewer laterals;  installation of new sewer manholes and rehabilitation of existing sewer manholes;  and restoration of existing asphalt pavements, driveways, sidewalks, and curbs.

            (Estimated completion date, continuing through April 2014)

 

WAIKIKI

Beachwalk Force Main Phase I:  2 Staging pits to be constructed along Ala Wai Boulevard from Kalakaua towards Ala Moana Boulevard for the microtunneling installation of new sewer line.

            (Estimated completion, continuing through April 2014)

 

Waikiki Sewers Rehabilitation/Reconstruction:  Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation along Kuhio Avenue between Namahana Street Kapuni Street.

            (Estimated completion date, continuing through April 2014)

 

WAIMALU

Waimalu Stream Maintenance Dredging   Project consists of maintenance dredging of accumulated sediment in Waimalu Stream and Punanani Channel.  Dredged material will be disposed of at designated ocean disposal site and upland location.

            (Estimated completion date, continuing through April 2014)

 

WAIPIO

Rehabilitation of Streets, Unit 47, Waipio  The work includes reconstruction of pavement and resurfacing of streets; reconstruction of curbs, gutters, tree trimming, root pruning and tree removal as necessary; pavement markings and markers, restoration of vehicular detector loops, adjustment of street monuments to new finish grade, and adjustment / reconstruction of utility manhole / valve box frames and covers to finish grade.

The affected roadways and limits of work are as follows:  Ka Uka Boulevard, Ukee Street, Waipio Uka Street, Moaniani Street, Lumikula Street, Kuala Street (Waiawa), Acacia Road (Waiawa)

            (Estimated completion date, December 2014)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

April 27, 2014 Sunday
5:00AM Starts
9:00AM Ends

DASH AND SPLASH BIATHLON sponsored by Kailua Canoe Club. The event is expected to have 400 participants. Run- It will start at Kailua Boat Ramp, to Kawailoa Rd., to Aalapapa Dr., counterclockwise around Lanika Lp. bike path, to Mokulua Dr., to Kawailoa Rd., to Lihiwai Rd., to end at boat ramp.  Swim- 800 yards parallel to shore down to finish area.  Contact:  Lapule Schultz 220-8251, E-mail:  lapule-schultz@notes.k12.hi.us or Joan Malama 258-0914 or Darrylynn Ferreira 864-0692 

 

April 27, 2014 Sunday
7:00AM Starts
2:00PM Ends

JOHN KELLEY HALEIWA METRIC CENTURY RIDE sponsored by Hawaii Bicycling League. The event is expected to have 800 riders. It will start/end at Kaiaka Beach Park.  25K:  Kaiaka Beach Park, to Haleiwa Rd., to Paala Rd., to  Kamehameha Hwy., Ehukai Beach Park turnaround, to Kam Hwy., to Joseph Leong Hwy., to Haleiwa Rd., to end at Kaiaka Beach Park.  50/100K:  Kaiaka Beach Park, to Haleiwa Rd., to Paala Rd., to Kamehameha Hwy., 50K turnaround at Kahuku High School.  100K turnaround at Swanzy Beach Park, to Kam Hwy., to Joseph Leong Hwy., to Haleiwa Rd., to end at Kaiaka Beach Park.  No lanes will be closed, except for start of ride. Contact:  HBL 735-5756, Fax:  735-6679, For more info, check out their website:  http://www.hbl.org/

 

April 27, 2014 Sunday
6:30AM Starts
11:00AM Ends

HONOLULU 5K RUN FOR KIDS sponsored by Honolulu 5K. The event is expected to have 4,000 runners.  5K ROUTE- It will start at Beretania St., kkhd of Richards St –kkhd bound on Beretania – right onto Alapai St- onto South St – right onto Pohukaina St – right onto Punchbowl St - left onto King St -  left onto Richards St - right onto Queen St - right onto Bishop St – right onto Beretania St-right onto Alakea St - left onto King St - left on Richards St.-right on Beretania St.- right on Punchbowl St.-left onto King St finish area.  WALK ROUTE:  It will start at King St kkhd bound –left onto Alapai St-left onto Beretania St-left onto Punchbowl St-left onto King St finish area.  Contact: Chis Gardner  372-8885, E-mail:  jon@pacificsportevents.com  For more info,  check out their website: http://www.honolulu5k.org/

 

April 27, 2014 Sunday
8:00AM Starts
2:00PM Ends

KALIHI HAND TOOL COMPETITION sponsored by Slim's Power Tools.  The event is expected to have 1,500+ participants.  Traffic will be diverted starting 8pm 4/26 for setup. The event will close Republican Street, all traffic lanes/sidewalk areas, from Libby St. to Kalihi St. Contact: Rand Okemura 841-0902 or 927-9995, Fax: 845-4180 Email: rjokemura@slimspowertools.com

 

May 2, 2014 Friday
8:00PM Starts
2:00AM Ends

FIRST FRIDAY STREET FESTIVAL sponsored by Arts District Merchant Association. The event is expected to have 1,000+ participants.  HOTEL ST., will be closed from Nuuanu Ave to Smith St. approx 8 pm. Contact: Sandy Pohl 521-1812,  For more info, visit their website:  http//www.artsdistricthonolulu.com

 

May 3, 2014  Saturday
6:00PM Starts
11:00PM Ends

WAIKIKI SPAM JAM STREET FESTIVAL sponsored by SJ Foundation.  The event is expected to have 8,000+ participants.  Traffic will be diverted starting 4 pm for setup. The event will close Kalakaua Avenue, all traffic lanes/sidewalk areas, from Seaside Ave. to Kaiulani Avenue. Contact:  Karen Winpenny 255-5927, E-mail:  kwinpenny@hawaii.rr.com  

 

- END -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391.