You are here: Main / Customer Services / Public Communications Division / 2014 / 03/07/14 Traffic Advisory: Lane closures for Honolulu rail transit project | ||||
March 7, 2014 Traffic Advisory: Lane closures for Honolulu rail transit project The Honolulu Authority for Rapid Transportation (HART) would like to inform drivers about lane closures next week related to design and construction work for the Honolulu rail transit project. Motorists are advised that work along the 20-mile rail route from East Kapolei to Ala Moana Center will require lane closures during non-peak traffic hours. For the safety of both the work crews and motorists, the public is advised to proceed with caution through these areas. Drivers should anticipate possible traffic delays or use alternate routes during work hours, and provide a safe distance between their vehicles and workers and equipment. EWA Farrington Highway between Kualakai Parkway (North-South Road) and Old Fort Weaver Road is closed in both directions through April for utility relocation and column work for the elevated rail guideway. The 24/7 road closure allows work crews to safely relocate major utility lines along a narrow two-lane stretch of Farrington Highway, just west of the Kahi Mohala Behavioral Center. Drivers traveling between East Kapolei and the Ewa/Waipahu region will still be able to use either the H-1 Freeway on the north end of Kualakai Parkway, or Kapolei Parkway on the south end. The contractor will conduct staggered lane closures of the eastbound and westbound lanes along Farrington Highway between the Kunia Road overpass and Old Fort Weaver Road Loop from Sunday, March 9 to Saturday, March 15. Drivers heading in either direction may be diverted to a temporary lane during the work. WAIPAHU The outside lanes of Farrington Highway east of Waipahu High School will be closed for streetlight relocation work on Monday, March 10 from 8:30 a.m. to 3 p.m. On Tuesday, March 11, the inside lanes of Farrington Highway will be closed for similar work from 8:30 a.m. to 3 p.m. PEARL CITY Overnight lane closures will take place along Kamehameha Highway between Waimano Home Road and Kuala Street from Monday, March 10 to Friday, March 14 between 7:30 p.m. and 5:30 a.m. for utility relocation work:
Two westbound lanes of Kamehameha Highway between Waimano Home Road and Puu Poni Street will be closed overnight from Monday, March 10 to Friday, March 14 between 7:30 p.m. and 5:30 a.m. the following morning. Overnight lane closures will take place along Kamehameha Highway between Kuleana Road and Puu Poni Street near the HECO-Waiau power plant from Monday, March 10 to Friday, March 14 between 8 p.m. and 5:30 a.m. for utility relocation work:
AIEA Lane closures will take place along Kamehameha Highway between Hekaha and Kanuku streets near Best Buy for drill shaft test work:
Two westbound and one eastbound lane of Kamehameha Highway between Lipoa Place and Pali Momi Street near Pearl Kai Shopping Center will be closed from Monday, March 10 to Friday, March 14 between 7:30 p.m. and 5:30 a.m. for soil tests:
PEARL HARBOR Lane closures will take place at the following location from Monday, March 10 to Friday, March 14 between 8:30 a.m. and 3 p.m. for soil testing:
KALIHI/IWILEI Daytime and overnight lane closures will take place at the following locations for soil testing and trench work:
DOWNTOWN/KAKAAKO Road closures will take place this weekend in downtown Honolulu on Saturday, March 8 and Sunday, March 9 between 7 a.m. and 8:30 p.m. for trench work:
Overnight lane closures will take place in downtown Honolulu from Sunday, March 9 to Thursday, March 13 between 8:30 p.m. and 4 a.m. the following morning for soil testing:
Daytime lane closures will take place in Kaka'ako for soil testing and trench work:
For updates on work days and times, visit the project website at www.honolulutransit.org or contact our hotline at 566-2299. - END - Media Contact: Scott Ishikawa. (808) 768-6172. cell: (808) 227-2350. |