Thursday, March 31, 2011

City and County of Honolulu News Releases

You are here:  Main / Customer Services / Public Communications Division / 2011 / 03/30/11 Construction Weekly Report for week of April 3, 2011

 

CONSTRUCTION WEEKLY REPORT

 

Scheduled construction for week beginning April 3, 2011 for the Department of Design & Construction, Civil Division (Construction Management Branch), & Wastewater Division (Construction Management Branch).  Roadwork is normally done between the hours of 8:30 AM & 3:30 PM unless otherwise noted. 

 

***Motorists should anticipate intermittent lane closures when traversing through the area.

 

AIEA

 

Aiea Heights Drive Emergency Roadway Improvements:

 

Work includes road/slope stabilization and pavement resurfacing/rehabilitation (incl. installation of metal guardrail and plastic lumber lagging) below Analio Place and above the horseshoe turn. 

            (Estimated completion date, July 2011)

           

 

 

Local Rehabilitation of Streets, Phase 1 (IDIQ#2)

 

Finished paving Keeaumoku St. from Kaihee St to Mauka End and Kalihi St from Maliu St to Mauka End

 

         

 

AINA HAINA

 

Curb Ramps at Various Locations, FY 2009 (C) – East Hind Dr./Hind Iuka Dr., East Hind Dr./Olapa St./Opihi St., East Hind Dr./Uhiuhi St. and East Hind Dr./Manauwea St.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory/street signs. Adjustment of utility boxes.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, May 2011)

           

 

Kalanianaole Highway Sewer System Improvement:

 

CIPP rehabilitation of 24" and 30" sewer lines along Kalanianaole Highway between Wailupe Beach Park and Paiko Drive.

 

            (Estimated completion date, June 2011)

           

 

EWA

 

Curb Ramps at Various Locations, FY 2009 (C) – Aaha Pl./North Rd.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory/street signs. Adjustment of utility boxes.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, May 2011)

           

 

Miscellaneous Drainage Improvements at Various Locations (Pohakupuna Road)

 

Construct additional drain manholes on the existing drain line.

 

            (Estimated completion date, May 2011)

         

 

 

HALAWA

 

WORK COMPLETED ~ FINAL INSPECTION PENDING

Aliipoe Ditch Reconstruction – Halawa Heights, Lalawai Drive and Kahema Place area:

 

Demolish, remove and reconstruct existing concrete drainage ditch.  Construct maintenance access ramp and driveway.  Install storm drain manholes, drain inlets, trench drain, and 18" drain pipes.  Install new chain link fence.

 

            (Estimated completion date, March 2009)

           

 

Foster Village Sewer Rehabilitation/Reconstruction:

 

Installation of new 8" and 12" sewer lines and a sewer manhole along Piikea Street, Haloa Drive, Olino Street, Hakupapa Street, Punihi Street, and Palanihu Place.

 

            (Estimated completion date, May 2011)

           

 

Rehabilitation of Secondary Streets at Pearl City – Ulune Street (Kahuapaani Street to Kulawea Street), Aiealani Place (Halawa Heights Road to end), Fernridge Place (Halawa Heights Road to end), Halawa Heights Road (Fernridge Place to Mauka end), Hele Mauna Place (Halawa Heights Road to end), Kaimakani Street (Moanalua Road to Ulune Street), Palaialii Place (Halawa Heights Road to end), and Palaialii Way (Palaialii Place to end):

 

Paving completed.  Punch list for manhole adjustment remaining. 

 

            (Estimated completion date, April 2010)

 

 

WORK COMPLETED – FINAL INSPECTION PENDING

HAWAII KAI

 

Curb Ramps at Various Locations, FY 2008 (X), Kaumakani Street / Lunalilo Home Road, Kalanipuu Street / Lunalilo Home Road:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory/street signs. Installation of new Heco handhole and conduits. Adjustment of HECO pullbox. Installation of pavement striping, markings and markers.

 

            (Estimated completion date, January 31, 2011)

           

 

 

HONOLULU

 

Airport Sewer Structural Rehabilitation/Reconstruction:

 

CIPP rehabilitation of 42" sewer lines at the intersection of Lagoon Dr. and Aolele Street.

 

            (Estimated completion date, August 2011)

           

 

Ala Moana Boulevard Sewer Reconstruction (Emergency), Street Lighting and Resurfacing Joint Project:

 

Pilot tube 16", 18", 24" sewer lines along Ala Moana Boulevard between Piikoi and Atkinson.

 

            (Estimated completion date, April 2011)

           

 

Ala Moana Trunk Sewer Rehabilitation:

 

CIPP rehabilitation of 69" sewer lines along Ala Moana Boulevard between Keawe Street and Kamakee Street.

 

            (Estimated completion date, February 2012)

           

 

WORK COMPLETED - FINAL INSPECTION PENDING

Curb Ramps at Various Locations, FY 2008 (X), South Beretania Street / Ward Avenue:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory / street signs. Utility adjustments. Upgraded traffic signal system.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, December 10, 2010)

           

 

 

Curb Ramps at Various Locations, FY 2009 (B), Palolo and Kaimuki:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory/street signs. Installation of pavement striping, markings and markers.

 

            (Estimated completion date, June, 2011)

           

 

Houghtailing Street Area Sewer Rehabilitation:

 

Installation and rehabilitation of sewer lines and construction of new manholes along School Street.

 

            (Estimated completion date, May 2011)

           

 

WORK COMPLETED – FINAL INSPECTION PENDING

Iolani Avenue Retaining Wall:

 

Construction of new CRM fence wall and installation of soil nail tie backs and reinforced shotecrete facing along the retaining wall at 625 Iolani Avenue fronting Dole Community Garden. Restore A.C. sidewalk fronting new CRM wall.  Remove existing trees and re-plant new trees in the Dole Community Garden..

 

            (Estimated completion date, January 2011)

           

 

Iwilei Road and North King Street Drainage Improvements – Intersection of Iwilei Road and North King Street:

 

Repair 18-inch and 12-inch drain lines, pavement restoration work, curb, gutter and sidewalk restoration, striping, and pavement marking restoration, the construction of sewer jackets and the reconstruction of a curb ramp flare.

 

            (Estimated completion date, June 2011)

           

 

Kahanu Street, School Street, Umi Street Relief Sewer:

 

Various sewer repairs along Umi Street, King Street, Richard Lane, Stanley Street, Wilcox Lane, Kahanu Street, Kalihi Street, Dilingham Boulevard, Puuhale, School Street between Liliha and McGrew Lane.

 

            (Estimated completion date, June 2012)

           

 

Kalihi/Nuuanu Area Sewer Rehabilitation Phase 1A and 1C:

New sewer line and manhole installation on Dillingham Blvd, Puuhale Road, Mokauea Street, and Kalihi Street.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

           

            (Estimated completion date, March 2010)

           

 

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village:

 

Paving completed. Punch list work remaining.

 

            (Estimated Completion Date, April 2010)

           

 

Mokauea Street Improvements between North King Street and Dillingham Boulevard:

 

Reconstruction concrete curbs and gutters, driveway and some sidewalks; construct new curb ramps; reconstruct and resurface asphalt roadway.  Post paving activities include installation of permanent pavement markings, adjust utilities to finish grade, and re-install traffic loop detectors.

 

            (Estimated Completion May 2011)

 

Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program:

Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves.

Re-grade swale and adjust Drain inlet to provide positive Drainage into existing Drain system. Reconstruct concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams.

 

At the intersection of Ahua Street and Awaawaloa Street, abandon existing storm drain on Ahua Street and install new storm drain MH on upstream end of abandoned pipe.

 

            (Estimated completion date, April 2011)

             

 

Peterson Lane and Pua Lane Sewer Rehabilitation:

 

New sewer line and manhole installation in complete on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Repaving of King, Peterson and Pua lane is complete. Punchlist items and reconstruction of Tamashiro market driveway remain.  One lane in each direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

 

 

            (Estimated completion date, December 2009)

           

 

Final Inspection in Progress

Punchbowl Street and Lusitana Street Drainage Improvements:

 

The work consists of drainlines and manholes rehabilitation with Cast-in-place-pipe (CIPP) in Punchbowl Street, and 24-inch drainline and curb replacement in Lusitana Street. One lane road closure will be limited to 8:30 a.m. to 3:30 p.m., Monday thru Friday, except for County furlough and holidays, work will begin on January 31, 2011. One lane will be closed to traffic at Lusitana Street and police office will be on-site during work hours.

 

            (Estimated completion date, March 2011)

           

 

Final Inspection in Progress

Rehabilitation of Localized Streets, Phase 5A – Kahala to Kaimuki Area

The work includes localized reconstruction of pavement and resurfacing of the streets indicated below; reconstruction of curbs, gutters, sidewalks and driveways are included; tree trimming, pruning and removal will be performed as necessary; post paving activities include permanent pavement markings and adjustment of utility manhole frames and covers to grade.  The affected roadways and limits of work are as follows:

 

            18th Avenue, from Harding Avenue to Diamond Head Road

19th Avenue, from H-1 Freeway to Kilauea Avenue including TMK: 32039051

            20th Avenue, from H-1 Freeway to Kilauea Avenue

            21st Avenue, from Harding Avenue to Kilauea Avenue

            22nd Avenue, from Harding Avenue to End

            Ahakea Street, from Aukai Avenue to Elepaio Street

            Ahina Street, from Ahakea Street to Aukai Avenue

            Ahuli Place, from Pahoa Avenue to End

            Alae Street, from Elepaio Street to Onaha Street

            Amau Street, from Hunakai Street to Pueo Street

            Apuwai Place, from Kilauea Avenue to End

            Aukai Avenue, from Kealaolu Avenue to Kahala Avenue

            Elepaio Street, from Kilauea Avenue to Kahala Avenue

            Farmers Road, from Kealaolu Avenue to Ulumaika Street

            Hakaka Place, from Hakaka Street to End

            Hakaka Street, from Palekaua Street to End

            Honua Street, from Onaha Street to Kolohala Street

            Hopeloa Place, from Puu Panini Avenue to End

            Huanui Place, from Huanui Street to End

Huanui Street, from 22nd Avenue to Puu Panini Avenue including TMK: 32061018

            Hunakai Street, from Waialae Avenue to Kahala Avenue

            Hunalewa Street, from 22nd Avenue to Huanui Street

            Hunapaa Street, from Huanui Street to End

            Iiwi Street, from Onaha Street to Kolohala Street

            Ipo Place, from 22nd Avenue to End

            Kaalawai Place, from Diamond Head Road to End

            Kaikoo Place, from Papu Circle to End

            Kaikuono Place, from Papu Circle to End

            Kaimanahila Street, from Paikau Street to Hakaka Street

            Kaimuki Avenue, from 18th Avenue to Luawai Street

            Kala Place, from Aukai Avenue to Kahala Avenue

            Kaualio Place, from 22nd Avenue to End

            Kealaolu Place, from Kealaolu Avenue to End

            Koae Place, from Koae Street to End

            Koae Street, from Hunakai Street to Amau Street

            Koloa Street, from Kahala Avenue to Elepaio Street

            Kolohala Street, from Onaha Street to Elepaio Street

            Kuana Street, from Onaha Street to Kolohala Street

            Kulamanu Street, from Kahala Avenue to Kulamanu Place

            Luakaha Place, from Luakaha Street to End

            Luakaha Street, from Luawai Street to End

            Luawai Place, from Luawai Street to End

            Luawai Street, from 20th Avenue to Pahoa Avenue

            Makaiwa Street, from Kilauea Avenue to Pueo Street

            Makalike Place, from 22nd Avenue to End

            Malapua Place, from 22nd Avenue to End

            Maunaloa Avenue, from 18th Avenue to 22nd Avenue

            Moa Street, from Pueo Street to Makaiwa Street

            Noio Street, from Onaha Street to Kolohala Street

            Onaha Street, from Kilauea Avenue to Kolohala Street

Pahoa Avenue, from Kilauea Avenue to Moa Street and from 18th Avenue to 22nd Avenue

            Paikau Street, from 22nd Avenue to Kahala Avenue

            Palekaua Place, from Palekaua Street to End

            Palekaua Street, from Puu Panini Avenue to Hakaka Street

            Pana Place, from Paikau Street to End

            Panini Loop, from Puu Panini Avenue to Puu Panini Avenue

            Pilialo Street, from Luawai Street to Kaimuki Avenue

            Poka Place, from Poka Street to End

            Poka Street, from Paikau Street to Diamond Head Road

            Pokapahu Place, from Paikau Street to End

            Pueo Street, from Kahala Avenue to Hunakai Street

            Puulani Place, from Hunakai Street to End

            Puu Panini Avenue, from Kilauea Avenue to 22nd Avenue

            Ulili Street, from Onaha Street to Kahala Avenue

            Ulumaika Street, from Hunakai Street to Hunakai Street

            Ulupua Place, from 22nd Avenue to End

            Waikui Street, off Kalanianaole Highway

            Waiohinu Drive, from Makaiwa Street to Makaiwa Street

 

            (Estimated Completion November 23, 2010)

         

 

Rehabilitation of Localized Streets, Phase 5B – Kaimuki, Diamond Head and Kapahulu Areas

The work includes localized reconstruction of pavement and resurfacing of the streets indicated below; reconstruction of curbs, gutters, sidewalks and driveways are included; tree trimming, pruning and removal will be performed as necessary; post paving activities include permanent pavement markings and adjustment of utility manhole frames and covers to grade.  The affected roadways and limits of work are as follows:

 

Aloalo Place, from Harding Avenue to End

Alohea Avenue, from 6th Avenue to Makapuu Avenue

Belser Street, from Kaimuki Avenue to Harding Avenue

Bethshan Road, from 12th Avenue to End

Brokaw Street, from Kanaina Avenue to Alohea Avenue

Campbell Avenue, from Monsarrat Avenue to Collins Street

Castle Street, from Kanaina Avenue to 6th Avenue

Catherine Street, from Kanaina Avenue to Alohea Avenue

Charles Street, from Kapahulu Avenue to 4th Avenue

Coconut Avenue, from Kalakaua Avenue to Hibiscus Drive

Collins Street, from Campbell Avenue to Kepa Street

Crater Place, from Crater Road to End

Crater Road, from 12th Avenue to End

Diamond Head Circle, from Monsarrat Avenue to End

Diamond Head Road, from Poni Moi Street to Beach Road

Duval Street, from Kanaina Avenue to Upper Street

Edna Street, from Trousseau Street to Alohea Avenue

Ekela Avenue, from Date Street to End

Esther Street, from Kanaina Avenue to Upper Street

Francis Street, from Kanaina Avenue to Alohea Avenue

George Street, from Campbell Avenue to Alohea Avenue

Hayden Street, from Campbell Avenue to Alohea Avenue

Herbert Street, from Kapahulu Avenue to 6th Avenue

Hibiscus Drive, from Poni Moi Street to Coconut Avenue

Hinano Street, from Campbell Avenue to Trousseau Street

Holei Street, from Leahi Avenue to Noela Street

Hoolulu Street, from Kapahulu Avenue to 6th Avenue

Hunter Street, from Kapahulu Avenue to Winam Avenue

James Street, from Upper Street to Alohea Avenue

Kaimuki Avenue, from Kapiolani Boulevard to 4th Avenue and from 6th Avenue to 18th Avenue

Kalakaua Avenue, from Poni Moi Street to Coconut Avenue

Kamuela Avenue, from Date Street to Kapahulu Avenue

Kana Place, from Ocean View Drive to End

Kanaina Avenue, from Kaunaoa Street to Monsarrat Avenue and from Monsarrat Avenue to Private Section

Kaunaoa Street, from Leahi Avenue to Trousseau Street

Kepa Street, from Wauke Street to Collins Street

Kepuhi Street, from Trousseau Street to Alohea Avenue

Kiele Avenue, from Poni Moi Street to Coconut Avenue

Kikeke Avenue, from Pahoa Avenue to H-1 Freeway End and from Pahoa Avenue to H1 Freeway End

Kilauea Avenue, from 6th Avenue to 3812 Kilauea Avenue

Kokohead Avenue, from Pahoa Avenue to 12th Avenue and from Waialae Avenue to Harding Avenue

Leialoha Street, from Olokele Avenue to End

Lincoln Avenue, from Kapahulu Avenue to 6th Avenue

Lukepane Avenue, from Date Street to Leialoha Street

Mahina Avenue, from Kokohead Avenue to 15th Avenue

Makaleka Avenue, from Date Street to End

Makapuu Avenue, from Diamond Head Road to Kilauea Avenue

Makini Street, from Campbell Avenue to Trousseau Street

Malie Place, from Pokole Street to End

Martha Street, from Campbell Avenue to 6th Avenue

Maunalei Avenue, from 9th Avenue to Makapuu Avenue

Maunaloa Avenue, from 6th Avenue to 18th Avenue

McCorriston Street, from Trousseau Street to Alohea Avenue

Mokihana Street, from Kapahulu Avenue to 4th Avenue         

Nikolo Street, from Holei Street to Noela Street

Noela Street, from Paki Avenue to End

Ocean View Drive, from Pahoa Avenue to Kilauea Avenue

Olokele Avenue, from Date Street to End

Olu Street, from Kapahulu Avenue to 4th Avenue

Owena Street, from Holei Street to Noela Street

Paahana Street, from Maunaloa Avenue to Kaimuki Avenue

Pahoa Avenue, from Kokohead Avenue to 18th Avenue

Palani Avenue, from Date Street to Winam Avenue

Palima Place, from Pahoa Avenue to 4th Avenue

Paliuli Street, from Kapahulu Avenue to 4th Avenue

Pokole Street, from Alohea Avenue to Kilauea Avenue

Poni Moi Road, from Paki Avenue to Hawaii School for Girls Entrance

Pualei Circle, from Leahi Avenue to End

Sunset Avenue, from 12th Avenue to Kilauea Avenue

Sunset Place, from Sunset Avenue to End

Trousseau Street, from Wauke Street to Monsarrat Avenue and from Diamond Head Road to End

Upper Street, from Duval Street to James Street

Wauke Street, from Campbell Avenue to Trousseau Street

Wela Street, from Trousseau Street to Alohea Avenue

Williams Street, from Kapahulu Avenue to Winam Avenue

Winam Avenue, from Hayden Street to Olokele Avenue

1st Avenue, from Waialae Avenue to Harding Avenue

2nd Avenue, from Waialae Avenue to Lincoln Avenue

3rd Avenue, from Waialae Avenue to Kaimuki Avenue

4th Avenue, from Paliuli Street to Winam Avenue

5th Avenue, from Pahoa Avenue to H-1 Freeway

6th Avenue, from Pahoa Avenue to Alohea Avenue

7th Avenue, from Pahoa Avenue to Alohea Avenue

8th Avenue, from Pahoa Avenue to Alohea Avenue

9th Avenue, from Pahoa Avenue to Maunalei Avenue

10th Avenue, from Maunalei Avenue to Alohea Avenue

11th Avenue, from Pahoa Avenue to Kilauea Avenue

12th Avenue, Pahoa Avenue to Alohea Avenue

13th Avenue, from 150' makai of Waialae Avenue to Pahoa Avenue

14th Avenue, from 150' makai of Waialae Avenue to Kaimuki Avenue

15th Avenue, from Waialae Avenue to Harding Avenue and H-1 Freeway to Kilauea Avenue

16th Avenue, from Waialae Avenue to Kilauea Avenue

17th Avenue, from H-1 Freeway to Kilauea Avenue

 

           

            (Estimated Completion November 2011)

         

 

Rose Street/Kam IV Road (SMPR 66) and Richard Lane/Linapuni Street (SMPR 67) Sewer Rehabilitation:

 

Installation of new sewer lines/manholes and reconnection of existing sewer laterals along Richard Lane, Linapuni Street, Kahauiki Street, Kamehameha IV Road between Kahuiki Street and Owene Lane, and Rose Street.

 

            (Estimated completion date, July 2011)

           

 

Rehabilitation of Secondary Streets at Ala Wai:

 

The project includes excavating, reconstructing and resurfacing asphalt concrete pavements and base; providing smooth lateral transitions at all streets and driveways; reconstructing base at bus stop locations; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings. The affected roadways and limits of work are as follows:

 

            Kapiolani Boulevard: From Date Street to South King Street, paving completed.

            Isenberg Street: From Kapiolani Boulevard to Bingham Street, paving completed.

            Punch list work remaining.

 

            (Estimated completion date, January 2011)

           

 

 

Rehabilitation of Secondary Streets at Downtown:

 

The project will demolish, remove and dispose of existing pavements in the Honolulu Area.    Adjust manholes and monuments to road grades.  Restore all pavement striping, markings and markers.  Collect GPS data on manholes, street monuments, valve boxes, fire hydrants, and other features as directed by the City before construction begins.  The affected roadways and limits of work are as follows:

 

            Kukui: From Queen Emma to Aala, paving completed, pavement stripping on going

Queen Emma: From Beretania to School St. paving completed, pavement stripping on going  

            School St: From Queen Emma to Aala paving and adjusting manholes on going

            Aala: From Beretania to School St. paving completed.

           

 

            (Estimated completion date, May 2011)

           

 

Rehabilitation of Various Streets on Oahu:  IDIQ #1

 

Pacific Heights Drive and Kamehameha Highway in Haleiwa paving completed. Various Streets in Kapahulu paving completed. Kaneohe will be paved next.

 

            (Estimated completion date, December 2008)

           

 

Rehabilitation of Secondary Streets at Kaimuki – Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street:

 

Paving completed. Punch list work remaining

 

            (Estimated completion date, June 2010)

 

 

 

 

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Kapahulu: 4th ave, 5th ave, Hookipa Way, Pahoa Ave, Kaimuki Ave, Olu St, Mokihana St, Paliuli St and Charles St. and Kulamanu Place:

 

The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.

 

Olu St from 4th Ave to 6th Ave, Mokihana St from 4th Ave to Mooheau Ave and Kulamanu Pl from Kulamanu St to End are done.

 

            (Estimated completion date, June 22, 2013)

           

 

 

Rehabilitation of Secondary Streets at Makiki - Kinau St from Alapai St to Waiau Pl, Wilder Ave from Spencer St to Dole St. and Dole St from Wilder Ave to St. Louis Dr.:

 

The project will demolish, remove and dispose of existing pavements in Honolulu area. Resurface or reconstruct these streets with asphalt concrete pavement.  Adjust manholes and monuments to road grades.  Restore all pavement striping, markings and markers.  Collect GPS data on manholes, street monuments, valve boxes, fire hydrants, and other features as directed by the City before construction begins.

 

Wilder Ave and Dole St, paving completed.  Kinau St. will start after the state project in the Kinau off ramp is completed.

 

 

            (Estimated completion date, March 2011)

           

 

Saint Louis Heights Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights.  The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street.

 

            (Estimated completion date, May 2011)

           

 

Sewer Manhole and Pipe Rehabilitation at Various Locations – Phase 2:

 

Various manhole rehabilitation along Nimitz Highway between Pacific Street and Sumner Street.

 

            (Estimated completion date, September 2011)

           

 

Wilhelmina Rise Sewer Rehabilitation:

 

Installation of cured in place pipe (CIPP), lateral rehabilitation, and replacement of sewer lines by open trench.

 

(Estimated completion date, May 2011)

           

 

 

 

KAILUA

SUSPENDED ~ AWAITING CONTRACTOR TO ADDRESS DEFICIENCIES

Rehabilitation of Streets, Unit 42 – Kainehe Street (Kihapai Street to Kailua Road) and Hamakua Drive (Kailua Road to Keolu Drive):

 

Paving, traffic signal upgrades, adjustment utility manholes frames and covers to grade, vehicle detector loops and pavement markings complete.  Installation of traffic signs, bridge deck joints and deficiency require intermittent lane closures and punchlist items.

 

            (Estimated completion date, November 2007)

           

 

WORK COMPLETED ~ AWAITING CONTRACTOR TO ADDRESS DEFICIENCIES

Rehabilitation of Streets, Unit 46 – Kailua Road (Hamakua Bridge to Kuulei Road); and Kuulei Road (Kailua Road to Kainalu Drive):

 

Reconstruct curbs, gutters, sidewalks and roadway pavement; construct new curb ramps and concrete bus pads; resurface roadway, reinstall signage, replace vehicle detector loops and install permanent pavement markings. The contractor is working on Kainalu Drive in Kailua.  Work is expected to be completed by December 2009.

 

            (Estimated completion date, December 2009)

           

 

Rehabilitation of Secondary Streets in Kailua

 

Repaving work is complete in Kailua.  Punch list remaining.

 

           

 

Rehabilitation of Streets, Unit 52 – Keolu Drive (Kalanianaole Highway to Akahai Street); Keolu Drive (Akaakaawa Street to Wanaao Road):

 

Cold planing; resurfacing and reconstruction of asphalt concrete pavements (ACP); adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, sidewalks and Driveways; reconstruction of concrete catch basins; and construction of concrete and asphaltic concrete bus pads.

 

            (Estimated completion date, May 2010)

           

 

 

Wanaao Road/Keolu Drive Reconstructed Sewer:

 

Installation of new sewer line along Keolu Drive (Nanialii Street to Wanaao Road) and Wanaao Road (Keolu Drive to Auwinala Road).

 

            (Estimated completion date, April 2010)

           

 

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Aikahi Park

 

The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.

 

Slurry seal completed.

 

            (Estimated completion date, June 22, 2013)

           

 

 

KANEOHE  

 

Flood Control Improvements at Various Locations FY 2008 – Kaneohe, Kailua & Waipio:

 

Demolish and reconstruct new concrete and asphalt concrete ramps and driveways.  Repair existing concrete ditch and adjust utility frames, covers and boxes to finish grade.

 

            (Estimated completion date, May, 2011)

           

 

Rehabilitation of Kamehameha Highway Bridge Over Heeia Stream – Kamehameha Highway in Heeia:

 

Repair of concrete delamination, spalls and cracks on existing bridge structure; removal and replacement of sidewalk platform; painting of the bridge parapet, chain link fence, and sidewalk's steel structure.

 

            (Estimated completion date, June 2011)

           

 

 

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Kaneohe: Mokulele Dr and Kaneohe Bay Dr.

 

The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.

 

Slurry seal is in process.

 

            (Estimated completion date, June 22, 2013)

           

 

 

WORK COMPLETED. FINAL INSPECTION PENDING

MAKAKILO

 

Curb Ramps at Various Locations, FY 2008 (X), Anipeahi Street / Makakilo Drive, Panana Street (Mauka Lani Elementary School Exit):

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory/street signs.  Installation of new HECO handhole. Adjust Hawaiian Telcom pullbox. Upgraded traffic signal system. Installation of pavement striping, markings and markers.

 

            (Estimated completion date, December 10, 2010)

           

 

 

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Honokai Hale

 

The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.

 

Crack sealing completed.  Slurry seal is next.

 

            (Estimated completion date, June 22, 2013)

           

 

 

 

MANOA

 

Miscellaneous Drainage Improvements at Various Locations (Loulu Street)

 

Construct concrete drain inlets, connect to existing catch basin, and install drain pipes and cleanouts.

 

            (Estimated completion date, April 2011)

           

 

 

NUUANU

 

Localized Rehabilitation of Streets, Phase 3, Nuuanu (Dowsett Highlands), Pacific Heights, Pauoa Valley, Moanalua Valley to west of Fort Shafter, Salt Lake towards Foster Village:

 

Paving completed. Punch list work remaining.

 

            (Estimated completion date, May 2010)

           

 

 

Rehabilitation of Kimo Drive Bridge Over Nuuanu Stream, Bridge No. 260

Repair spalls concrete guardrails and bridge girders.

 

            (Estimated completion date Jan 2011)

           

 

PALOLO

 

Curb Ramps at Various Locations, FY 2009 (C) – Hoanoho Pl./Palolo Ave.:

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory/street signs. Adjustment of utility boxes.  Installation of pavement striping, markings and markers.

 

            (Estimated completion date, May 2011)

           

 

Rehabilitation of Secondary Streets at Kaimuki – Palolo Avenue, Waialae Avenue to 10th Avenue in Palolo Valley

 

Paving completed. Punch list work remaining.

.

 

            (Estimated completion date, May 2010)

           

 

PEARL CITY

 

Waimalu Sewer Rehabilitation/Reconstruction Phase I:

 

Installation of new sewer lines/man holes and reconnection of existing sewer laterals along Hekaha, Kanuku, Lokowai, Lii-Ipo, Pahemo, and Olepe.

 

            (Estimated completion date, June 2011)

           

 

Waimalu Sewer Rehabilitation/Reconstruction Phase II:

 

Installation of new 8" and 12" sewer lines along Hekaha Street between Kanuku Street and Moanalua Road.

 

            (Estimated completion date, October 2011)

           

 

Manana Infrastructure Improvements, Phase VI – Connector Road (Kuala Street to Kuahaka Street)

 

Construct 60-foot wide roadway from Kuala Street to Kuahaka Street. The work includes, vector control; clearing, grubbing and grading; installation of new storm drain, Heco, Hawaiian Telcom, street light and traffic signal systems; concrete slab protection for existing sewer and water lines; grade adjustments in private lots; new noise and retaining walls, chain link fence and gates: reconstruction of existing drain, water and sewer MHs and valves to new finish grade; installation of curbs, gutters, sidewalks, driveways, curb ramps and sidewalk culverts; installation of irrigation system and landscape improvements; tree removal and pruning in private lots; road paving; pavement markings and markers and street signs.

 

90-day maintenance period for street trees in progress (1/12/11 to 4/12/11).

           

            (Estimated completion date, including landscape maintenance period, April 2011)

           

 

 

(WORK COMPLETED, FINAL INSPECTION CONDUCTED ON 6/8/10. PUNCHLIST WORK FOR SPALLED AND DELAMINATED AREAS ALONG BRIDGE ABUTMENTS AND PIERS BEING ADDRESSED)

Bridge Rehabilitation At Various Locations

Moanalua Road Bridge Over Waimalu Stream (Bridge No. 910):

 

Partial demolition and removal of existing curbs, gutters and sidewalks on bridge deck. Reconstruct curbs, gutters, sidewalk and A.C. pavement. Repair spalled, delaminated and hollow sounding areas in bridge soffit, abutments and pier. Repair bridge parapet, metal railing and expansion and cold joints.

 

            (Estimated completion date, April 2011)

 

 

Rehabilitation of Secondary Streets at Pearl City – Hoolaulea Street below Moanalua Road  (Waimano Home Road to Hoomoe Road), Nanakai Place (Nanakai Street to end), Nanakai Street (Waimano Home Road to Hoomalu Street), Puu Kipa Street ( Nanakai Street to Nanakai Street):

 

Paving completed.  Punch list remaining. 

 

 

            (Estimated completion date, December 2009)

 

 

PEARLRIDGE

 

Rehabilitation of Secondary Streets at Pearl CityKaonohi Street ( Kaonohi Place to entire loop), and Kaonohi Street (Kamehameha Highway to Moanalua Road):

 

Paving completed.  Punch list remaining. 

 

            (Estimated completion date, December 2009)

 

 

PUPUKEA

 

Pupukea Road Rockfall Mitigation Phase I – Pupukea, Oahu:

 

The work consists of clearing vegetation within the project limits, scaling boulders and unstable rocks or installing rock dowels (where appropriate), applying shotcrete (where required), installing rock fall protection fences, drapery system and landscaping. One traffic lane will be closed during work hours at Pupukea Road with police performing traffic control duties. Contractor is scheduled to begin work in March 2011.

 

            (Estimated completion date, August 2011)

 

 

WORK COMPLETED. FINAL INSPECTION PENDING

SALT LAKE

 

Curb Ramps at Various Locations, FY 2008 (X), Salt Lake Boulevard (Stadium Entrance and Exit close to Kam Highway):

 

Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory / street signs. Utility adjustments. Upgraded traffic signal system. Installation of pavement striping, markings and markers.

 

            (Estimated completion date, December 10, 2010)

           

 

 

Rehabilitation of Streets, Phase 1 (aka IDIQ #2) – Ala Mahamoe St, Ala Lilikoi St, Ala Napunani St, Salt Lake Blvd, Kanewai St, Kaluawaa St, Kamakini St, Waiomao Rd, Ala Alii St, Anapa St, Haloa Sr, Halupa St, Holapa St, Kukila Pl, Kukila St, Laakea Pl, Laakea St, Lehia St, Loina Pl, Luapele Dr, Luapele Pl, Mahie Pl, Mahie St, Molehu Dr, Molina St, Naulu Pl, Olaloa St, Olino St, Opua St, Palahinu Pl, Piikea Pl, Piikea St, Puanakau St, Ukali St, Uila St, Wawe Pl, Kahikolu Pl, Kahikolu Way, Likini St, Makaala St, Manuwa Dr, Miko St, Pakini St, Ukana St, Wanaka St

 

Resume paving at Salt Lake side streets from Wanaka St. to Pakini St.

Put down permanent stripping at Ala Mahamoe St.

 

 

 

WAHIAWA

 

Rehabilitation of Streets, Unit 58 – California Avenue (Kamehameha Highway to mauka end of California Avenue):

 

Cold planing; resurfacing and reconstruction of asphalt concrete pavement; adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, berms, sidewalks and Driveways; and construction of concrete and asphalt concrete bus pads.

 

            (Estimated completion date, January 2012)

           

 

 

WAIANAE

 

Mailiili Stream Flood Control Improvements – Near Halona Road and Puuhulu Road:

 

Removal and reconstruction of damaged concrete channel lining, construction of new channel access ramp near Halona Road Bridge, and construction of overflow side-drains on the channel banks.

 

            (Estimated completion date, July 2011)

           

 

 

Work completed; continue landscape maintenance

Mailiili Stream Restoration – Near Mailiili Road:

 

Removal of fill material including concrete rubble, uncompacted material, asphalt concrete, etc., removal of access ramp, installation of erosion control blanket on stream banks, and planting of channel bed with wetland vegetation.  Implementation, maintenance and removal of BMPs.

 

            (Estimated completion date, February 2011)

           

 

 

WAIKIKI

Beachwalk Force Main Phase I:

 

2 Staging pits to be constructed along Ala Wai Boulevard from Kalakaua towards Ala Moana Boulevard for the microtunneling installation of new sewer line.

 

            (Estimated completion date, June 2011)

           

 

Kalakaua Avenue Sewer Rehabilitation:

 

Installation of new 8" and 10" sewer line along Kalakaua Avenue between Philip Street and Kapiolani.

 

            (Estimated completion date, August 2011)

           

 

Rehabilitation of Secondary Streets at Kaimuki – Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street

 

Paving completed. Punch list work remaining.

 

 

            (Estimated completion date, June 2010)

           

 

 

Rehabilitation of Streets, Phase 1 (aka IDIQ #2) – Ena Rd, McCully St, Niu, Keoniana, Pau, Kuamoo, Kalaimoku st, Olohana st, Kalakaua Ave, Makee Rd, Cartwright Rd, Lemon Rd, Ohua Ave, Paoakalani Ave, Keolohilani Ave, Koa Ave, Prince Edward, Liliuokalani, Koa Ave, Kaiulani Ave, Lauula St, Seaside, Royal Hawaiian, Lewers, Helumoa Rd, Beachwalk, Paoa Pl, Kalia Rd, Saratoga Rd, Waimami Way, Kaneloa Pl, Ainakea Way, Pualani Way, Paoakalani Ave, Mountain View, Tusitala, Kapuni, Kapili, Kaiulnai Ave, Kanekapolei St, Walina St, Nahua St, Nohonani St, Aloha Dr, Seaside, Kaiolu, Laniu, Kalaimoku, Olohana, Namahana, Kalaimoku

 

Currently paving side streets, Wainani Way, Kaneloa Pl, Ainakea Way, Pualani Way and Paoakalani Ave.

 

           

 

 

WAIMANALO

 

Retaining Walls Along Waikupanaha Street, Box Culvert No. 5

 

Construction work complete.  Establishing ground cover remaining item.

           

            (Estimated completion date:  November 4 2010)

           

 

WAIPAHU

 

Rehabilitation of Secondary Streets at Pearl City – Paiwa Street (Farrington Highway to Waipahu Street), Waipahu Street (Hianakiu Street to Kaupu Place), Makoa Street (Puia Street to end to end), Puia Street (Anonui Street to Eleu Street, and Heahea Street to deadend):

 

Paving completed.  Punch list for remaining. 

 

(Estimated completion date, December 2009)

 

Waipahu Street/Plantation Village Sewer Reconstruction:

 

Installation of new sewer lines and manholes along Waipahu Street between Awamoi and Mokuola.

 

            (Estimated completion date, July 2011)

           

 

 

 

No comments:

Post a Comment