December 2, 2010

ROAD WORK WEEKLY REPORT

 

Scheduled road work for the week beginning December 5, 2010, for the Department of Design construction, Civil Division (Construction Management Branch), and Wastewater Division (Construction Management Branch) is listed below.  Road work is normally done between the hours of 8:30 AM and 3:30 PM unless otherwise noted.

 

AIEA

Local Rehabilitation of Streets, Phase 1 (IDIQ#2).  Paving Keeamoku St. from Kaihee St to Mauka End and Kalihi St from Maliu St to Mauka End.

 

AINA HAINA

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Aina Haina:  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Hind Iuka Dr from Mona St to End slurry seal is done.

            (Estimated completion date, June 2013)

 

HALAWA

Rehabilitation of Secondary Streets at Pearl City – Ulune Street (Kahuapaani Street to Kulawea Street), Aiealani Place (Halawa Heights Road to end), Fernridge Place (Halawa Heights Road to end), Halawa Heights Road (Fernridge Place to Mauka end), Hele Mauna Place (Halawa Heights Road to end), Kaimakani Street (Moanalua Road to Ulune Street), Palaialii Place (Halawa Heights Road to end), and Palaialii Way (Palaialii Place to end):  Paving completed.  Punch list for manhole adjustment remaining.

            (Estimated completion date, December 2010)

 

HAWAII KAI

Curb Ramps at Various Locations, FY 2008 (X), Kaumakani Street / Lunalilo Home Road, Kalanipuu Street / Lunalilo Home Road:  Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory / street signs. Installation of new Heco handhole and conduits. Adjustment of Heco pullbox. Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2010)

 

HONOLULU

Rehabilitation of Secondary Streets at Ala Wai  The project includes: excavating, reconstructing and resurfacing asphalt concrete pavements and base; providing smooth lateral transitions at all streets and driveways; reconstructing base at bus stop locations; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings. The affected roadways and limits of work are as follows:   Kapiolani Boulevard: From Date Street to South King Street, Isenberg Street: From Kapiolani Boulevard to Bingham Street

            (Estimated completion date, January 2011)

 

Amelia Street Relief Sewer – Amelia Street and adjoining School Street:  Installation of a new 16" sewer line underground along Amelia Street and portion of School Street at Amelia Street

            (Estimated completion date, December 2010)

 

Iolani Avenue Retaining Wall:  Construction of new CRM fence wall and installation of soil nail tie backs and reinforced shotecrete facing on retaining wall at 625 Iolani Avenue fronting Dole Community Garden. Restore A.C. sidewalk fronting new CRM wall.  Remove existing trees and re-plant new trees in Dole Community Garden.

            (Estimated completion date, December 2010)

 

Rehabilitation of Localized Streets, Phase 5A – Kahala to Kaimuki Area

Post Paving Activities in-progress.  The work includes permanent pavement markings and adjustment of utility manhole frames and covers to grade.  The affected roadways and limits of work are as follows:

 

18th Avenue, from Harding Avenue to Diamond Head Road, 19th Avenue, from H-1 Freeway to Kilauea Avenue including TMK: 32039051, 20th Avenue, from H-1 Freeway to Kilauea Avenue, 21st Avenue, from Harding Avenue to Kilauea Avenue, 22nd Avenue, from Harding Avenue to End, Ahakea, Street, from Aukai Avenue to Elepaio Street, Ahina Street, from Ahakea Street to Aukai Avenue, Ahuli Place, from Pahoa Avenue to End, Alae Street, from Elepaio Street to Onaha Street, Amau Street, from Hunakai Street to Pueo Street, Apuwai Place, from Kilauea Avenue to End, Aukai Avenue, from Kealaolu Avenue to Kahala Avenue

 

Elepaio Street, from Kilauea Avenue to Kahala Avenue, Farmers Road, from Kealaolu Avenue to Ulumaika Street, Hakaka Place, from Hakaka Street to End, Hakaka Street, from Palekaua Street to End, Honua Street, from Onaha Street to Kolohala Street, Hopeloa Place, from Puu Panini Avenue to End, Huanui Place, from Huanui Street to End, Huanui Street, from 22nd Avenue to Puu Panini Avenue including TMK: 32061018, Hunakai Street, from Waialae Avenue to Kahala Avenue, Hunalewa Street, from 22nd Avenue to Huanui Street, Hunapaa Street, from Huanui Street to End, Iiwi Street, from, Onaha Street to Kolohala Street, Ipo Place, from 22nd Avenue to End

 

Kaalawai Place, from Diamond Head Road to End, Kaikoo Place, from Papu Circle to End, Kaikuono Place, from Papu Circle to End, Kaimanahila Street, from Paikau Street to Hakaka Street, Kaimuki Avenue, from 18th Avenue to Luawai Street, Kala Place, from Aukai Avenue to Kahala Avenue, Kaualio Place, from 22nd Avenue to End, Kealaolu Place, from Kealaolu Avenue to End, Koae Place, from Koae Street to End, Koae Street, from Hunakai Street to Amau Street, Koloa Street, from Kahala Avenue to Elepaio Street, Kolohala Street, from Onaha Street to Elepaio Street, Kuana Street, from Onaha Street to Kolohala Street, Kulamanu Street, from Kahala Avenue to Kulamanu Place

 

Luakaha Place, from Luakaha Street to End, Luakaha Street, from Luawai Street to End, Luawai Place, from Luawai Street to End, Luawai Street, from 20th Avenue to Pahoa Avenue, Makaiwa Street, from Kilauea Avenue to Pueo Street, Makalike Place, from 22nd Avenue to End, Malapua Place, from 22nd Avenue to End, Maunaloa Avenue, from 18th Avenue to 22nd Avenue, Moa Street, from Pueo Street to Makaiwa Street, Noio Street, from Onaha Street to Kolohala Street, Onaha Street, from Kilauea Avenue to Kolohala Street

 

Pahoa Avenue, from Kilauea Avenue to Moa Street and from 18th Avenue to 22nd Avenue, Paikau Street, from 22nd Avenue to Kahala Avenue, Palekaua Place, from Palekaua Street to End, Palekaua Street, from Puu Panini Avenue to Hakaka Street, Pana Place, from Paikau Street to End, Panini Loop, from Puu Panini Avenue to Puu Panini Avenue, Pilialo Street, from Luawai Street to Kaimuki Avenue

Poka Place, from Poka Street to End, Poka Street, from Paikau Street to Diamond Head Road, Pokapahu Place, from Paikau Street to End, Pueo Street, from Kahala Avenue to Hunakai Street, Puulani Place, from Hunakai Street to End, Puu Panini Avenue, from Kilauea Avenue to 22nd Avenue, Ulili Street, from Onaha Street to Kahala Avenue, Ulumaika Street, from Hunakai Street to Hunakai Street, Ulupua Place, from 22nd Avenue to End, Waikui Street, off Kalanianaole Highway, Waiohinu Drive, from Makaiwa Street to Makaiwa Street

            (Estimated Completion December 23, 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1A and 1C:  New sewer line and manhole installation on Mokauea Street, Kalani Street and Kino Street.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.            (Estimated completion date, December 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1B:  New sewer line and manhole installation on Kopke Street.  Kopke Street and Gulick Ave.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, December 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1D:  New sewer line and manhole installation on Captain Cook and  Lolena Street.  Lane Closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, December 2010)

 

Kalihi Nuuanu Area Sewer Rehabilitation Phase 1G:  New sewer line and manhole installation on Kuakini Street (between Nuuanu Avenue and Pali Highway) is ongoing.  Lane closures Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, December 2010)

 

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Kapahulu: 4th ave, 5th ave, Hookipa Way, Pahoa Ave, Kaimuki Ave, Olu St, Mokihana St, Paliuli St and Charles St. and Kulamanu Pl.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Olu St from 4th ave to 6th ave, Mokihana St from 4th ave to Mooheau ave and Kulamanu Pl from Kulamanu St to End are done.

            (Estimated completion date, June 2013)

 

Local Rehabilitation of Streets, Phase 1 (IDIQ#2)  Paving Keeamoku St. from Kaihee St to Mauka End and Kalihi St from Maliu St to Mauka End

 

Rehabilitation of Secondary Streets at Makiki; Kinau St from Alapai St to Waiau Pl, Wilder Ave from Spencer St to Dole St. and Dole St from Wilder Ave to St. Louis Dr.  The project will demolish, remove and dispose of existing pavements in Honolulu area. Resurface or reconstruct these streets with asphalt concrete pavement.  Adjust manholes and monuments to road grades.  Restore all pavement striping, markings and markers.  Collect GPS data on manholes, street monuments, valve boxes, fire hydrants, and other features as directed by the City before construction begins.

            (Estimated completion date, March 2011)

 

Mapunapuna Industrial Subdivision Phase One of Tidal Flooding Remediation Program.  Remove existing flap gates and install new check valves at outlet pipes in State channel fronting Kam Highway. Construct new DMH upstream of new check valves. Re-grade swale and adjust DI to provide positive drainage into existing drain system. Upgrade concrete wall at outlet pipes at State channel. Remove debris and sediment from existing storm drains and channel area. Dewater State channel and install temporary dewatering dams.  At the intersection of Ahua Street and Awaawaloa Street, abandon existing storm drain on Ahua Street and install new storm drain MH on upstream end of abandoned pipe.

            (Estimated completion date, December 2010)

 

Mokauea Street Improvements between North King Street and Dillingham Boulevard:  Reconstruction concrete curbs and gutters, driveway and some sidewalks; construct new curb ramps; reconstruct and resurface asphalt roadway.  Post paving activities include installation of permanent pavement markings, adjust utilities to finish grade, and re-install traffic loop detectors.

            (Estimated Completion April 2011)

 

Rehabilitation of Secondary Streets at Kaimuki – Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street.  Paving completed, working on manhole adjustments.

            (Estimated completion date, December 2010)

 

Peterson Lane and Pua Lane Sewer Rehabilitation:  New sewer line and manhole installation on King Street (between Dillingham Blvd. and Peterson Lane), Pua Lane and Peterson Lane.  Sewerwork is ongoing on Pua Lane.  Repaving of King, Peterson and Pua lane to follow after sewer work is complete.  Pua Lane – One lane in mauka bound direction will be closed Monday thru Friday, 8:30 a.m. to 3:30 p.m.

            (Estimated completion date, December 2010)

 

Punchbowl Street and Lusitana Street Drainage Improvements:  The work consists of drainlines and manholes rehabilitation with Cast-in-place-pipe (CIPP) in Punchbowl Street, and 24-inch drainline and curb replacement in Lusitana Street. One lane road closure will be limited to 8:30 a.m. to 3:30 p.m., Monday thru Friday, except for County furlough and holidays. Work will begin in December 2010.

            (Estimated completion date, February 2011)

 

Saint Louis Heights Sewer Rehabilitation:  Installation of cured in place pipe (CIPP), manhole rehabilitation, and lateral rehabilitation throughout Saint Louis Heights.  The contractor will also install new sewer lines via pipe bursting at 3 locations along Saint Louis Drive and one easement location between Saint Louis Drive and Frank Street.

            (Estimated completion date, December 2010)

 

Curb Ramps at Various Locations, FY 2008 (X), South Beretania Street / Ward Avenue:  Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory / street signs. Utility adjustments. Upgraded traffic signal system.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2010)

 

Sewer rehabilitation on various streets on Wilhelmina Rise.  Installation of cured in place pipe (CIPP), lateral rehailitation, and replacement of sewer lines by open trench.

            (Estimated completion date December 2010)

 

KAILUA

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Aikahi Park.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal is in process.

            (Estimated completion date, June 2013)

 

Kalaheo Avenue/Mokapu Road/Aikahi Loop Sewer Rehabilitation:  Installation of Cured In Place Pipe along Mokapu Boulevard, from the intersection of Mokapu and Kalaheo, and Aikahi Loop.

            (Estimated completion date, December 2010)

 

Rehabilitation of Kawailoa Road Bridge over Kaelepulu Stream, Bridge No. 411:  Work includes repair of spalls in the concrete elements; replacement of the deteriorated pedestrian walkway and railing at the upstream side of the bridge; repair of deck joints; replacement of the vehicular guardrail system; and traffic safety improvements at the bridge approaches.

            (Estimated completion date, December 2010)

 

Rehabilitation of Streets, Unit 52 – Keolu Drive (Kalanianaole Highway to Akahai Street); Keolu Drive (Akaakaawa Street to Wanaao Road):  Cold planing; resurfacing and reconstruction of asphalt concrete pavements (ACP); adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, sidewalks and Driveways; reconstruction of concrete catch basins; and construction of concrete and asphaltic concrete bus pads.

            (Estimated completion date, December 2010)

 

Seismic Retrofit at City Bridges FY09, Keolu Drive Bridge, and Auloa Road Bridge:  Work consists of making seismic retrofit improvements that include installing: stainless steel bolsters at the deck slab,

concrete bolsters/creep blocks, stainless steel plates across expansion joints, and other miscellaneous bridge improvements.

            (Estimated completion date, December, 2010)

 

Wanaao Road/Keolu Drive Reconstructed Sewer:  Installation of new sewer line along Wanaao Road between Hahani Street and Aoloa Road.

            (Estimated completion date, December 2010)

 

KANEOHE

Curb Ramps at Various Locations, FY 2009 (X) – Hui Iwa Street / Hui Kelu Street / Hui Aeko Street:  Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing stop sign.  Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2010)

 

Rehabilitation of Kamehameha Highway Bridge Over Heeia Stream – Kamehameha Highway in Heeia:  Repair of concrete delamination, spalls and cracks on existing bridge structure; removal and replacement of sidewalk platform; painting of the bridge parapet, chain link fence, and sidewalk's steel structure.

            (Estimated completion date, June 2011)

 

Kaneohe Bay Drive Trunk Sewer Reconstruction:  Installation of new sewer lines, new manholes, and cured in place pipe (CIPP).  Work will occur on Kaneohe Bay Drive between Mokapu Road and Kuono Place, Kaimalu Place and Way, Ikeanani Drive, and Kuakoa Place.

            (Estimated completion date December 2010)

 

Kapunahala Road Retaining Wall near 45-866 Anoi Road  Construction of a concrete retaining wall and railing.  Restore AC pavement, AC sidewalk and AC curb.  Traffic detours will be provided after working hours.

            (Estimated completion date, December 2010)

 

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Kaneohe: Mokulele Dr and Kaneohe Bay Dr.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Slurry seal is in process.

            (Estimated completion date, June 2013)

 

MAKAKILO

Curb Ramps at Various Locations, FY 2008 (X), Anipeahi Street / Makakilo Drive, Panana Street (Mauka Lani Elementary School Exit):  Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory / street signs.  Installation of new Heco handhole. Adjust Hawaiian Telcom pullbox. Upgraded traffic signal system. Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2010)

 

Rehabilitation of Streets Indefinite Delivery/Indefinite Quantity IDIQ #3 – Honokai Hale.  The scope of work to be performed by the Contractor under this contract may include, but is not limited to: cold planning; slurry seal; crack seal; reconstructing curb and gutters/rolled curbs; resetting of lava rock curbs; aboricultural work; adjusting street survey monuments, utility manholes/boxes, frames and covers; installing pavement striping and markings; and reinstalling vehicle detector loops.  Crack sealing is in process.

            (Estimated completion date, June 2013)

 

MANOA

Manoa Valley Drainage Improvements at 3088 and 3090 Kahewai Place: Removal of existing concrete headwall and drain pipe, installation of new drain manhole and 18" RCP drain pipe, and construction of CRM drain outlet structure and base.

            (Estimated completion date, December 2010)

 

NUUANU

Rehabilitation of Kimo Drive Bridge Over Nuuanu Stream, Bridge No. 260  Repair of spalls, concrete guardrails and bridge girders.

 

PALOLO

Rehabilitation of Secondary Streets at Kaimuki – Palolo Avenue, Waialae Avenue to 10th Avenue in Palolo Valley.  Paving completed, working on manhole adjustments.

            (Estimated completion date, December 2010)

 

PEARL CITY

Rehabilitation of Secondary Streets at Pearl City – Hoolaulea Street below Moanalua Road  (Waimano Home Road to Hoomoe Road), Nanakai Place (Nanakai Street to end), Nanakai Street (Waimano Home Road to Hoomalu Street), Puu Kipa Street ( Nanakai Street to Nanakai Street):  Paving completed.  Punch list for manhole adjustment remaining.

            (Estimated completion date, December 2010)

 

Manana Infrastructure Improvements, Phase VI – Connector Road (Kuala Street to Kuahaka Street)  Construct 60-foot wide roadway from Kuala Street to Kuahaka Street. The work includes, vector control; clearing, grubbing and grading; installation of new storm drain, Heco, Hawaiian Telcom, street light and traffic signal systems; concrete slab protection for existing sewer and water lines; grade adjustments in private lots; new noise and retaining walls, chain link fence and gates: reconstruction of existing drain, water and sewer MHs and valves to new finish grade; installation of curbs, gutters, sidewalks, driveways, curb ramps and sidewalk culverts; installation of irrigation system and landscape improvements; tree removal and pruning in private lots; road paving; pavement markings and markers and street signs.

            (Estimated completion date, December 2010)

 

Waimalu Sewer Rehabilitation/Reconstruction Phase I:  Installation of new sewer lines/man holes and reconnection of existing sewer laterals along Hekaha, Kanuku, Lokowai, Lii-Ipo, Pahemo, and Olepe.

            (Estimated completion date, December 2010)

 

Protective Chain Link Fencing at Various Locations, FY-04 – Waimano Home Road:  

Removal and replacement of CMU wall, guardrails and chain link fence.

            (Estimated completion date, March 2011)

 

PEARLRIDGE

Rehabilitation of Secondary Streets at Pearl CityKaonohi Street ( Kaonohi Place to entire loop), and Kaonohi Street (Kamehameha Highway to Moanalua Road):  Paving completed.  Punch list for manhole adjustment remaining.

            (Estimated completion date, December 2010)

 

SALT LAKE

Protective Chain Link Fencing at Various Locations, FY-04 – Luaole Street:  Removal of damaged fence and installation of new chain link fence and posts.

            (Estimated completion date, March 2011)

 

Curb Ramps at Various Locations, FY 2008 (X), Salt Lake Boulevard (Stadium Entrance and Exit close to Kam Highway):  Construction of new curb ramps, sidewalks and A.C. transition.  Relocation of existing regulatory / street signs. Utility adjustments. Upgraded traffic signal system. Installation of pavement striping, markings and markers.

            (Estimated completion date, December 2010)

 

WAHIAWA

Rehabilitation of Streets, Unit 58 – California Avenue (Kamehameha Highway to mauka end of California Avenue):  Cold planing; resurfacing and reconstruction of asphalt concrete pavement; adjustment of utility manhole frames and covers; installation of pavement markings and vehicle loop detectors; reconstruction of existing concrete curbs, gutters, berms, sidewalks and Driveways; and construction of concrete and asphalt concrete bus pads.

            (Estimated completion date, December 2011)

 

WAIANAE

Mailiili Stream Flood Control Improvements – Near Halona Road and Puuhulu Road:  Removal and reconstruction of damaged concrete channel lining, construction of new channel access ramp near Halona Road Bridge, and construction of overflow side-drains on the channel banks.

            (Estimated completion date, July 2011)

 

Mailiili Stream Restoration – Near Mailiili Road:  Removal of fill material including concrete rubble, uncompacted material, asphalt concrete, etc., removal of access ramp, installation of erosion control blanket on stream banks, and planting of channel bed with wetland vegetation.  Implementation, maintenance and removal of BMPs.

            (Estimated completion date, February 2011)

 

WAIKIKI

Rehabilitation of Secondary Streets at Kaimuki – Palolo Avenue; Pahoa Avenue, 8th Avenue to Kokohead Avenue, 22nd Avenue to Kilauea Avenue; Kapahulu Avenue, Paki Avenue to Kalakaua Avenue; Paki Avenue, Kapahulu Avenue to Poni Mei Street.  Excavating, reconstructing and resurfacing asphalt concrete pavements and base; reconstructing base at bus stops; adjusting street monuments, utility manhole frames and covers; installing pavement markings; reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, December 2010)

 

WAIPAHU

Waipahu Street Retaining Wall Repair & 16th Avenue Boulder Basin Dam Wall Reconstruction:  Demolish and rebuild retaining wall, curb ramp, and portion of sidewalk adjacent to Waipahu Elementary School.  Awaiting staging area approval from DPR.  Tentative start of construction date set for October 23, 2009.

            (Estimated completion date December 2010)

 

Rehabilitation of Paiwa Street (Farrington Highway to Waipahu Street), Waipahu Street (Hianakiu Street to Kaupu Place), Makoa Street (Puia Street to end to end), Puia Street (Anonui Street to Eleu Street, and Heahea Street to deadend):  Cold planing, reconstructing, and resurfacing pavement.  Reconstructing base at bus stops.  Adjusting street monuments, utility manhole frames and covers, installing pavement markings, reconstructing existing asphalt concrete berms with drainage openings.

            (Estimated completion date, December 2010)

 

PARADES, WALKS, RACES AND OTHER STREET CLOSURES

 

December 5, 2010 Sunday
7:00AM Starts
9:00AM Ends

SAMS MEMORIAL 5K RUN sponsored by sponsored by RRCA/Mid Pacific Roadrunners Club. They expect to have 200 runners.  It will start on Monsarrat Ave. near Waikiki Shell, to Paki Ave., to Kalakaua Ave., to Monsarrat Ave., to Paki Ave., to Kalakaua Ave., end at Honolulu Marathon finish/Kapiolani Bandstand.  Contact: John Simonds 373-3609, Email:simondsj001@hawaii.rr.com  For more info, visit their website: http://www.mprrc.com/

 

December 5, 2010 Sunday
10:30AM Starts
12:30PM Ends

STREET BIKERS UNITED-TOYS FOR TOTS CARAVAN sponsored by Street Bikers United Hawaii. The event is expected to have 4,000 motorcycles.  It will start at Magic Island, to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave., to Diamond Hd. Rd. to end at Kapiolani Community College-DH campus.  Contact:  Ray Pagan 282-6419  E-mail:  onerican@hawaii.rr.com

 

December 5, 2010 Sunday 4:00PM Starts 
5:30PM Ends

PEARL CITY SHOPPING CENTER CHRISTMAS PARADE sponsored by Pearl City Shopping Center. The event is expected to have 1,000 marchers, 20 vehicles, & 5 floats.  It will start at Momilani Elementary School, to Hookiekie St., to Hoomoana St., to Hoolaulea St., to end at Pearl City Shopping Center.  Contact:  Kristin Anderson  593-1533  Fax: 593-0569

 

December 9, 2010 Thursday
6:30PM Starts
8:00PM Ends

KAPAHULU MOILIILI CHRISTMAS PARADE sponsored by Kapahulu-Moiliili Lions Club. The event is expected to have 250 marchers & 5 vehicles.  It will start at Kuhio Elementary School, to King St., to Beretania St., to Isenberg St., end at Old Stadium Park.  Contact: Glen Takamori 479-7139 Fax:  532-0110 Email: glen@mutualunderwriters.com

 

December 10, 2010  Friday
6:00PM Starts
11:00PM Ends

RONALD MCDONALD GIFT WRAP BLOCK PARTY sponsored by Murphy's Bar & Grill/Ronald McDonald House in Hawaii. The event is expected to have 300+ participants.  The event will close MERCHANT ST., all traffic lanes/sidewalk areas, from Nuuanu Ave. to Bethel St.  Contact Don Murphy 531-0422,  Fax: 533-4943

 

December 10, 2010 Friday
6:00PM Starts
8:00PM Ends

HALEIWA CHRISTMAS PARADE sponsored by North Shore Community Chamber of Commerce/Haleiwa Main Street. The event is expected to have 250 marchers, 25 vehicles, 4 floats & 4 bands.  It will start at Weed Circle, to Kamehameha Hwy., thru Haleiwa Town, to end at Haleiwa Beach Park.  Contact: Antya Miller  637-4558 Fax:  637-4556 Email: NorthShoreCCC@aol.com Website: http://www.gonorthshorehawaii.com/

 

December 11, 2010 Saturday 8:30AM Starts 
10:30AM Ends

AIEA COMMUNITY ASSOCIATION CHRISTMAS PARADE sponsored by Aiea Community Association. The event is expected to have 200 marchers, 10 vehicles, & 2 bands.  It will start at Pearlridge Elem School Parking lot , to Moanalua Rd., to Kaamilo St., to Ulune St., to Halewiliko St., to end at Aiea Sugar Mill Site.  Contact:  Claire J. Tamamoto 429-1282, Fax:  946-8347 Email: clairet@hawaii.rr.com

 

December 11, 2010 Saturday 10:00AM Starts 
11:30AM Ends

GENTRY WAIPIO COMMUNITY ASSOCIATION CHRISTMAS PARADE sponsored by Gentry Waipio Community Association. The event is expected to have 800 marchers, 13 vehicles, & 1 band.  It will start at Gentry Waipio SC, to Waipio Uka St., Ukee St., to Ka Uka Blvd., to Waipio Uka St., to end at Gentry Waipio SC.  Contact:  Sheryl Kaseli 671-2272  Fax: 671-0996 Email: gwca@hawaiiantel.net

 

December 11, 2010 Saturday 10:00AM Starts 
11:00AM Ends 

WAIMANALO CHRISTMAS PARADE sponsored by Waimanalo Construction Coalition. The event is expected to have 110 marchers, 20 vehicles, 6 floats & 3 bands.  It will start at Waimanalo District Park, to Hihimanu St., to Kumuhau St., to Humuniki St., to Kalanianaole Hwy., end at Waimanalo Beach Park. Contact:  Patty Teruya 768-3888 Fax: 768-1406  Email :Pteruya@Honolulu.gov

 

December 11, 2010 Saturday
3:00PM Starts
10:00PM Ends

XMAS BETWEEN THE AVENUES sponsored by Leeward Kai Canoe Club & Xmas Between the Avenues. The event is expected to have 2000 participants. The event will close MANO AVENUE., all traffic lanes/sidewalk areas, from Haleakala Ave. to Nanakuli Ave. Contact: Charlita Mahoe 306-0450 Email: charlitamahoe@aol.com

 

December 11, 2010 Saturday 3:00PM Starts 
5:00PM Ends

WAIPAHU CHRISTMAS PARADE sponsored by Lighthouse Outreach Center Assembly of God. The event is expected to have 10 vehicles.  It will start at Waipahu District Park at Paiwa St., to Farrington Hwy., to Pupukahi St., to Waipahu St., to Leoku St., to end at Leolua St. behind Waipahu Town Centerl.  Contact:  Joe Hunkin, Jr. 225-4589, E-mail:  joehunkin@clearwire.net

 

December 11, 2010 Saturday 5:00PM Starts 
7:00PM Ends

MANOA COMMUNITY CHRISTMAS PARADE sponsored by East Manoa Lions Club. The event is expected to have 800 marchers, 15 vehicles, 2 floats, & 4 bands.  It will start at Noelani School., to Woodlawn Dr, to Kolowalu St., to East Manoa Rd., to Lowrey Ave., to Manoa Rd., to Manoa Park finish.  Contact: Miyuki Matsuno 988-3819, E-mail:  matsunom001@hawaii.rr.com 

 

December 11, 2010 Saturday 6:00PM Starts 
8:00PM Ends

WEST OAHU HOLIDAY ELECTRIC LIGHT PARADE sponsored by Kapolei City Lights fka West Oahu Holiday Electric Light Parade. The event is expected to have 25  vehicles & 3 floats. It will start at Kapolei Fairgrounds at Kealanani Ave., to Farrington Hwy., to Kamokila Blvd., left into Uluohia St. and finish at Kapolei Hale. Contact:  Patty Teruya 527-5759, Fax:  550-6706

 

December 12, 2010 Sunday
5:00AM Starts
1:00PM Ends

HONOLULU MARATHON sponsored by Honolulu Marathon Association. They expect to have 35,000+ runners.  It will start on Ala Moana Blvd., near Queen St., to Ala Moana Blvd., ewa bound, to Nuuanu Ave., to King St., to Kapiolani Blvd., to Piikoi St., to Ala Moana Blvd., to Kalakaua Ave., to Monsarrat Ave., to Paki Ave., to Diamond Hd. Rd., to 18th Ave., to Kilauea Ave., to Waialae Ave., to Kalanianaole Hwy., to Hawaii Kai Dr., to Keahole St. to Kalanianaole Hwy., to Kealaolu Ave., to Kahala Ave., to Diamond Head Rd., to Kalakaua Ave., end at Honolulu Marathon finish/Kapiolani Bandstand. Roadways closed: 1)H1 Freeway closed at Waialae Ave. off ramp to Aina Koa Ave., 2)Kalanianaole Hwy., makai half closed for runners, between Aina Koa Ave. & Kawaihae St., mauka half converted to contra flow, 3)Kalanianaole Hwy., all lanes closed, between Kawaihao St. to Keahole St., Contact:  Honolulu Marathon Assn. 734-7200 Fax: 732-7057  For more info, visit their website:  http://www.honolulumarathon.org/   

 

- 30 -

 

Contact: Department of Design and Construction, Civil Design Division, Construction Management - 768-8839, Wastewater Management Division, Construction Management - 768-8794, Department of Transportation Services, TST Division 768-8391.