July 25, 2014 Traffic Advisory: Lane closures for Honolulu rail transit project The Honolulu Authority for Rapid Transportation (HART) would like to inform drivers about lane closures next week related to design and construction work for the Honolulu rail transit project. Motorists are advised that work along the 20-mile rail route from East Kapolei to Ala Moana Center will require lane closures during non-peak traffic hours. For the safety of both the work crews and motorists, the public is advised to proceed with caution through these areas. Drivers should anticipate possible traffic delays or use alternate routes during work hours, and provide a safe distance between their vehicles and workers and equipment. EWA Farrington Highway between Kualakai Parkway (North-South Road) and Old Fort Weaver Road will be closed overnight from Monday, July 28 to Friday, August 1 between 7 p.m. and 5 a.m. the following morning for utility relocation work. Drivers traveling between East Kapolei and the Ewa/Waipahu region during the overnight closures will still be able to use either the H-1 Freeway on the north end of Kualakai Parkway, or Kapolei Parkway on the south end. That nightly detour will run until the end of August. Left turns from Farrington Highway in Ewa onto Fort Weaver Road heading northbound will be restricted 24/7 through the end of August for column construction. Eastbound drivers using Farrington Highway will be asked to make a detour up Leoku Street to access Fort Weaver Road through either Leolua or Waipahu streets. The inside lanes of Farrington Highway and a portion of the Leoku Street intersection will also be closed during those same times. H-1 FREEWAY WAIAWA INTERCHANGE Two southbound lanes of the H-2 Freeway near the Waiawa Interchange (H-1/H-2 merge) will be closed overnight from Sunday, July 27 to Thursday, July 31 between 8:30 p.m. and 4 a.m. the following morning for utility work.
One eastbound lane of Farrington Highway between Leokane Street and Pupukahi Street will be closed overnight from Tuesday, July 29 to Friday, August 1 between 7 p.m. and 6 a.m. for utility work. The outside lanes of Farrington Highway in both directions in the same area will also be closed on Thursday, July 31 from 8:30 a.m. to 3:30 p.m. The outside lanes of Farrington Highway between Pupupuhi Street and Aniani Place will be closed on Wednesday, July 30 from 8:30 a.m. to 3:30 p.m. The westbound lanes of Farrington Highway between Aniani Place and Waipahu Depot Road will be closed overnight from Monday, July 28 to Friday, August 1 between 7 p.m. and 6 a.m. for utility work. The inside lanes of Farrington Highway between Waipahu Depot Road and Mokuola Street will be closed overnight from Monday, July 28 to Friday, August 1 between 7 p.m. and 6 a.m. for construction preparation work. The outside lanes of Farrington Highway near Waipahu High School will be closed overnight from Monday, July 28 to Friday, August 1 between 7 p.m. and 6 a.m. for construction preparation work.
PEARL CITY Two westbound lanes and two eastbound lanes along Kamehameha Highway will be closed overnight between Waiawa Road (near Leeward Community College) and Waimano Home Road from Monday, July 28 to Friday, August 1 between 8 p.m. and 7 a.m. for utility relocation/excavation work:
Two westbound lanes and one eastbound lane of Kamehameha Highway will be closed overnight between Puu Poni Street and Kuleana Road from Monday, July 28 to Friday, August 1 between 8 p.m. and 7 a.m.
AIEA/ALOHA STADIUM Two westbound and eastbound lanes of Kamehameha Highway between Kuleana Road and Hekaha Street will be closed overnight Monday, July 28 to Friday, August 1 between 8 p.m. and 7 a.m. for utility relocation work. Eastbound lanes of Kamehameha Highway between Pali Momi Street and Honomanu Street will be closed overnight Monday, July 28 to Friday, August 1 between 8 p.m. and 7 a.m. for utility relocation work. Eastbound traffic during night work may be directed to temporary lane on westbound side of highway.
The right eastbound lane of Kamehameha Highway between the Moanalua Freeway on-ramp and Salt Lake Boulevard will be closed 24 hours a day, seven days a week for roadway widening and installation of utility lines for traffic signals.
AIRPORT/PEARL HARBOR Overnight lane closures will take place at the Honolulu International Airport from Sunday, July 27 to Thursday, July 31 between 10 p.m. and 5 a.m. the following morning for soil testing:
KALIHI Intermittent lane closures will take place at the following locations from Sunday, July 27 to Thursday, July 31 between 8:30 p.m. and 4 a.m. for soil testing:
DOWNTOWN/KAKAAKO Daytime lane closures will take place in Kakaako at the following location from Monday, July 28 to Friday, August 1 from 8:30 a.m. to 3:30 p.m. for soil testing:
Queen Street between Cummins Street and Kamakee Street will be closed from Tuesday, July 29 to Thursday, July 31 between 10 p.m. and 6:30 a.m. for soil testing. Overnight lane closures will take place in Kakaako at the following location from Sunday, July 27 to Thursday, July 31 between 10 p.m. and 6 a.m. for soil testing:
For updates on work days and times, visit the project website at www.honolulutransit.org or contact our hotline at 566-2299. -END- Media Contact: Scott Ishikawa. (808) 768-6172. cell: (808) 227-2350. |